Extracted text: Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road construction project. Prepare a line of balance schedule for a contract of 125 sections using a target rate of build of 1.5 mile per week and each team working at their natural rate assume a minimum buffer time of 4 days between the operation and five 8 hrs days per week. 1. What is the overall duration of the project? 2. The date of the end of construction of 75% of the road. 3. The rate of work progress after 4 weeks. Activities Description Man hours Team size Depends on A Clearing 550 B Grubbing 550 Earth work 460 4 А, В Base 420 E Paving 330 3 F Finish Shoulders 200 1 E Move out 180 1 F 6,