Question 4 ACTIVITY PREDECESSORS DURATION (DAYS) P 3 4 R P 5 5 R,S 7 U R,S V 2 10 You are required to a) Draw the network diagram b) Calculate ES, EF, LS, LT c) Calculate slack time d) Identify...


Example of how to do it is on the 2nd picture.


Question 4<br>ACTIVITY<br>PREDECESSORS<br>DURATION (DAYS)<br>P<br>3<br>4<br>R<br>P<br>5<br>5<br>R,S<br>7<br>U<br>R,S<br>V<br>2<br>10<br>You are required to<br>a) Draw the network diagram<br>b) Calculate ES, EF, LS, LT<br>c) Calculate slack time<br>d) Identify critical path and activities<br>

Extracted text: Question 4 ACTIVITY PREDECESSORS DURATION (DAYS) P 3 4 R P 5 5 R,S 7 U R,S V 2 10 You are required to a) Draw the network diagram b) Calculate ES, EF, LS, LT c) Calculate slack time d) Identify critical path and activities
ESEF<br>Foward,<br>Add,<br>Bigget Value<br>Idantity Critical Path o<br>A.B,D,F<br>Slack tme<br>LSLF<br>Backward<br>Minus,<br>Smallest valuo<br>15<br>ES<br>A<br>5.<br>4<br>9.<br>15<br>5.<br>LF<br>0.<br>15<br>E<br>15<br>19<br>4.<br>LF<br>ES-LS<br>Ef-LF<br>15<br>

Extracted text: ESEF Foward, Add, Bigget Value Idantity Critical Path o A.B,D,F Slack tme LSLF Backward Minus, Smallest valuo 15 ES A 5. 4 9. 15 5. LF 0. 15 E 15 19 4. LF ES-LS Ef-LF 15