Question: 319 Due to an improper cost management plan, you are over budget and a new estimate is required to complete the project. Management asks you what the new estimate for the project will be....


Question: 319

Due to an improper cost management plan, you are over budget and a new estimate is required to complete the project. Management asks you what the new estimate for the project will be. Which of the following formulas is not used to find this new estimate?




(a) BAC / CPI


(b) AC + (BAC – PV)


(c) AC + (BAC – EV)


(d) AC + (BAC – EV) / (CPI * SPI)