Question 22 During assessing the project performance, the project manager found that the eamed value $2,400, the actual cost $2800, and the planned value $2,000. This means that the project is...





Question 22 During assessing the project performance, the project manager found that the eamed value $2,400, the actual cost $2800, and the planned value $2,000. This means that the project is schedule ahead on schedule exactly on the budget over running the budget