Question: 2. Determine the expected time and variances for each activity CPM AND PERT : 1. Determine a project network diagram. 3. Determine the EST, EFT, LST, LFT, SLACK TIME for each activity,...




Question:
2.    Determine the expected time and variances for each activity


CPM AND PERT :


1.    Determine a project network diagram.


3.    Determine the EST, EFT, LST, LFT, SLACK TIME for each activity, Critical Path and project completion time


4.    What is the probability that the project will be finished in 75 days?


5.    What is a new expected completion time when the project needs to be done on time with the 90 % probability.




Dec 10, 2021
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here