Question 1
Question options:
A)
Includes expert judgement
B)
includes change control meetings
C)
Which of the following is not true about integrated change tools?
A change control board approves or rejects change requests.
D)
includes project plan updates.
Question 2
Which of the following are not outputs of the project monitor and comtrol process?
Question options:
A)
Final transition.
B)
Plan updates.
C)
Document updates.
D)
Change requests.
Question 3
Which of the following terms is used to describe contested changes?
Question options:
A)
Complaints
B)
Mediation
C)
Forcing
D)
Claims
Question 4
Constuctive changes are .. ?
Question options:
A)
submitted to bids.
B)
viewed as negative.
C)
documented by project correspondence.
D)
postoned as long as possible.
Question 5
A workaround is .. ?
Question options:
A)
continuing to complete project work around the clock.
B)
an implementation of a contingency plan.
C)
is not planned in advance of the risk event occuring.
D)
a contingency plan.