Question 1Question options:A)higher than cumulative AC.B)higher than cumulative PV.C)
You know that your project is behind because the cumulative EV is much .. ?
lower than cumulative CPI.
D)
lower than cumulative PV.
Question 2
Which of the following shows that your project is 9% under budget?
Question options:
A)
EV = 100; PV = 110.
B)
PV = 100; AC = 110.
C)
AC = 100; EV = 110
AC = 110; EV = 100.
Question 3
CV = ?
AC - EV
EV - PV
EV - AC
PV - EV
Question 4
BAC = 200; AC = 120; EV = 80; CPI = .666
What is EAC if all future work is finished at budgeted rate?
200
120
240
160
Question 5
What is EAC if future work happens at the rate of actual work so far?
220, 240, 300, or 320?
220
320
300