Question 1 Question options: A) higher than cumulative AC. B) higher than cumulative PV. C) You know that your project is behind because the cumulative EV is much .. ? lower than cumulative CPI. D)...




Question 1
Question options:
A)
higher than cumulative AC.
B)
higher than cumulative PV.
C)


You know that your project is behind because the cumulative EV is much .. ?


lower than cumulative CPI.


D)


lower than cumulative PV.



Question 2


Which of the following shows that your project is 9% under budget?


Question options:


A)


EV = 100; PV = 110.


B)


PV = 100; AC = 110.


C)


AC = 100; EV = 110


D)


AC = 110; EV = 100.



Question 3


CV = ?


Question options:


A)


AC - EV


B)


EV - PV


C)


EV - AC


D)


PV - EV



Question 4


BAC = 200; AC = 120; EV = 80; CPI = .666


What is EAC if all future work is finished at budgeted rate?


Question options:


A)


200


B)


120


C)


240


D)


160



Question 5


BAC = 200; AC = 120; EV = 80; CPI = .666


What is EAC if future work happens at the rate of actual work so far?


220, 240, 300, or 320?


Question options:


A)


240


B)


220


C)


320


D)


300




Dec 02, 2021
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here