Question 1: Project Risk and Communication a. Your company has been requested by Client to prepare and submit a communication management plan. Prepare a communication management plan involving site...


Question 1:    Project Risk and Communication
a. Your company has been requested by Client to prepare and submit a communication management plan. Prepare a communication management plan involving site management team and client’s team and stakeholders.
b. Client Project Manager prepared a project risk matrix for the project to prepare the initial project budget. Prepare a project risk for this project.
     Question 2:   Application of AS 4000
a. AS4000 details specific lines of communication for the effective   processing of all progress payments (Monthly). Detail this process as outlined by AS4000, specifically identifying all relevant clauses that authorise the process.    Explain security of payment act and its application in your claim.
b. Explain how your company submitted the claims for dealing with ambiguities and errors in the documents with relevant clauses from AS 4000.
c. Your company decided to make ‘Claims for Variation’ for the                      additional works arising from the re-design of the seating.  Your claim should include possible surplus material or other alternative ways to deal with your order. What is the relevant clause under which Superintendent must have issued the direction to change the seating material?; explain with reasons.                          (4 marks)
d. Explain how your company dealt with discovery of ‘object of antiquity’ and how the Superintendent dealt with the claims for additional cost and time.
e. Your company noticed that the bolts shown on the drawings to fix the seatings were specified as galvanized iron bolts. Your company advised the Client that stainless steel bolts would be appropriate to avoid corrosion. Superintendent is considering your company’s suggestion. Explain how the Superintendent and    your company go about implementing the change of material for bolt.   (4 marks)
                                            Question 3: Earned Value Analysis
a. Based on the information provided in section H and other sections under “Further Information” carry out earned value analysis at the end of 6th month and calculate PV; EV; AC; CV; SV; CPI, SPI; BAC                    (4 marks)
Page 4 of 6
b. Estimate the cost at completion (EAC) using different methods; I. If the CPI is expected to be the same for the remainder of the project,  II. If future work will be accomplished at the planned rate; and  III. If both the CPI and SPI influence the remaining work;
a. Prepare a draft monthly report to the client detailing the status of the project as at the end of 6th month.
Question 5 : Estimating VOWD (Value of Work Done) and Accruals
In a pipeline project, following information has been provided to the Contract administrator. Contract Scope: Procure, deliver, install and test 3 Km long 300mm dia pipeline from point A to point B as shown in the drawings and specification. Contract period: 8 Months Bill of Quantities





Oct 07, 2019
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here