Question 1 Activity Based Costing for Kota Mills (25 marks) Kota Mills supply Divine Denim with the organic denim used in their production. After discussions with Helen about the service she was...

1 answer below »

View more »
Answered Same DayMay 04, 2021

Answer To: Question 1 Activity Based Costing for Kota Mills (25 marks) Kota Mills supply Divine Denim with the...

Khushboo answered on May 12 2021
145 Votes
Solution 1:
i. Data input sheet:
    Particulars
    Department 1
    Department 2
    Total
    Overhead costs
    19,332
    38,664
    57,996
    Direct labour hour
    55 hour
    90
     
    Direct labour costs
    $1,100
    $1,800
     
    
    
    
    
    
    
    
    
    Direct materials
    8 ounce
    13 ounce
    16 ounce
    Department 1
    $6,000
    $16,000
    $15,000
    Department 2
    $2,000
    $8,000
    $5,000
    Units produced
    1000
    4000
    2000
ii. Calculation of cost per bolt as per conventional process costing
    
    
    

    
    
    Particulars 
    8 ounce
    13 ounce
    16 ounce
    Total
    Units produced
    1000
    4000
    2000
    7000
    Department 1
     
     
     
     
    Direct material costs
    $6,000
    $16,000
    $15,000
    37000
    Direct labor costs
    $366.67
    $366.67
    $366.67
    1100
    Overhead costs
    6444
    6444
    6444
    19332
    Total cost of Department 1
    $12,811
    $22,811
    $21,811
    57432
     
     
     
     
     
    Department 2
     
     
     
     
    Direct material costs
    $2,000
    $8,000
    $5,000
    $15,000
    Direct labor costs
    $600
    $600
    $600
    $1,800
    Overhead costs
    12888
    12888
    12888
    $38,664
    Total cost of Department 2
    $15,488
    $21,488
    $18,488
    $55,464
     
     
     
     
     
    Total costs
    $28,299
    $44,299
    $40,299
    $1,12,896
    Cost per bolt
    $28.30
    $11.07
    $20.15
     
iii. Calculation of cost per bolt using ABC:
    
    
    
    
    
    
     
    cost driver
    8 ounce
    13 ounce
    16 ounce
    Total
    Cost pools and cost drivers
     
     
     
     
     
    Overhead costs:
     
     
     
     
     
    Cost to operate and maintain machine
    machine hour
    6001
    15998
    18002
    40,000
    Set up costs
    Number of set up
    1833
    5500
    3667
    11,000
    Inspection costs
    Inspection time
    996
    3996
    2004
    6,996
    Total overhead costs
     
    8830
    25494
    23672
    57996
    
    
    
    
    
    
    Particulars 
    8 ounce
    13 ounce
    16 ounce
    Total
    
    Units produced
    1000
    4000
    2000
    15000
    
    Direct material costs
    8,000
    24,000
    20,000
    52,000
    
    Direct labour costs
    660
    1320
    920
    2,900
    
    Total overhead costs
    8830
    25494
    23672
    57996
    
    Total costs
    17,490
    50,814
    44,592
    1,12,896
    
    Cost per bolt
    17.49
    12.70
    22.30
     
    
     
    Cost pool
     
     
     
     
    8 ounce
    13 ounce
    16 ounce
    Total
    machine hour
    500
    1333
    1500
    3333
    number of set up
    10
    30
    20
    60
    inspection time
    83
    333
    167
    583
iv. The costs under both the methods can be easily analyzed by referring to the below mentioned table:
     
    8 ounce
    13 ounce
    16 ounce
    Under conventional process costing
    
    
    
    Cost per bolt
    $28.30
    $11.07
    $20.15
    Under Activity based costing
    
    
    
    Cost per bolt
    17.49
    12.70
    22.30
The difference in the cost per bolt is due to the method used by the entity as in conventional method all the overhead costs are apportioned on the basis of the equality whereas in the activity- based costing the overhead costs are apportioned on the basis of the different cost pool and cost drivers. The cost of 8ounce bolt is overstated whereas the cost of 13 ounce and 16 ounce bolt has been understated in the process costing and the reason behind this wrong allocation is the selection of the wrong estimates and wrong allocation base. In the activity- based costing the overhead costs are apportioned among products on the basis of the activities performed and hence they are reflecting correct costs on the basis of the process involved in the production of each product.
v.    The activity- based costing system is the method which is used by the entity which identifies the activities and assigns the costs of each activity to all the different products on the basis of the actual consumption. This method allocates more overhead costs into direct costs in comparison to the conventional costing. In this case this method can be used by the entity to improve the operations as this method will identify the activity associated with the production of each product and cost will be allocated on the basis of the activities performed. Thus, no products will be overstated or understated as costs will be appropriately apportioned on the basis of the consumption of the activities. This method will increase the efficiency and all the products will be correctly measured and the cost can be assigned by the activities on the basis of the actual consumption.
Solution 2:
Preparation of flexible budget for April month:
    Flexible budget for 565 pair of jeans:
    
    
    
    
    Particulars
    Rate per unit
    Units required
    UOM
    Amount
    Direct material
    2
    5650
    Metre
    11300
    Direct labour
    2
    11300
    Hours
    22600
    Variable factory overheads
    0.4
    5650
    Hours
    2260
    Fixed factory overheads
    0.4
    12000
    Hours
    4800
    Fixed selling and admin expenses
     
     
     
    4500
    Variable selling and admin expenses
    2
    565
    Pair
    1130
     
     
     
     
     
    Total budgeted costs for 565 units
     
     
     
    46590
    Calculation of direct cost variances:
    
    
    
    
    Direct material cost...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30