Question 1 1 pts Every item on the WBS needs to be on the network diagram. Group of answer choices True False Flag this Question Question 2 1 pts The ____ for an activity is the latest possible time...




Question 1
1 pts
Every item on the WBS needs to be on the network diagram.
Group of answer choices
True
False


Flag this Question



Question 2



1 pts


The ____ for an activity is the latest possible time an activity might begin without delaying the project finish date.


Group of answer choices


late entry date


early start date


late start date


early entry date


Flag this Question



Question 3



1 pts


The arrows in a network diagram represent the activity sequencing or relationships between tasks.


Group of answer choices


True


False


Flag this Question



Question 4



1 pts


The outputs to schedule development include activity duration estimates and project document updates.


Group of answer choices


True


False


Flag this Question



Question 5



1 pts


Even though the delivery of new hardware may not be in the scope of a project, you should add an external dependency to it if required project activities depend on that delivery.


Group of answer choices


True


False


Flag this Question



Question 6



1 pts


Most managers are unfamiliar with any forms of scheduling.


Group of answer choices


True


False


Flag this Question



Question 7



1 pts


Schedule performance can be estimated by subtracting the original time estimate from how long it really took to complete the project.


Group of answer choices


True


False


Flag this Question



Question 8



1 pts


The goal of ____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.


Group of answer choices


estimating activity durations


sequencing activities


defining activities


estimating activity resources


Flag this Question



Question 9



1 pts


____ involves evaluating the reasons for dependencies and the different types of dependencies.


Group of answer choices


Defining activities


Estimating activity duration


Estimating activity resources


Sequencing activities


Flag this Question



Question 10



1 pts


Project managers must use discipline to control ____.


Group of answer choices


project bursts


project schedules


project critical paths


project dependencies


Flag this Question



Question 11



1 pts


In a ____ relationship, one task cannot finish before another finishes.


Group of answer choices


finish-to-finish


start-to-start


finish-to-start


start-to-finish


Flag this Question



Question 12



1 pts


In a ____ relationship, the "from" activity must finish before the "to" activity can start.


Group of answer choices


finish-to-finish


start-to-start


finish-to-start


start-to-finish


Flag this Question



Question 13



1 pts


One of PERT's main disadvantages is that it involves more work than CPM.


Group of answer choices


True


False


Flag this Question



Question 14



1 pts


____ is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.


Group of answer choices


Total float


Free slack


Total slack


Free time


Flag this Question



Question 15



1 pts


____ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.


Group of answer choices


Critical path analysis


Critical chain scheduling


A Gantt chart


PERT analysis


Flag this Question



Question 16



1 pts


The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.


Group of answer choices


estimating activity duration


defining activities


developing the schedule


sequencing activities


Flag this Question



Question 17



1 pts


Project schedules grow out of the basic documents that initiate a project.


Group of answer choices


True


False


Flag this Question



Question 18



1 pts


Project management software highlights the critical path in ____ on a network diagram.


Group of answer choices


green


red


blue


yellow


Flag this Question



Question 19



1 pts


The critical path always includes the most critical activities.


Group of answer choices


True


False


Flag this Question



Question 20



1 pts


____ dependencies are inherent in the nature of the work being performed on a project.


Group of answer choices


Mandatory


External


Discretionary


Internal


Dec 03, 2021
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here