Q 2/Draw the PERT network from the given information in the table below: Activity a M b 1 2 12 18 1 3 12 14 22 1 4 12 16 26 2 10 12 14 3 4 8. 4 5 4 13 16 4 6 6 8 10 2 10 Find the most likely time for...


Q 2/Draw the PERT network from the given<br>information in the table below:<br>Activity<br>a<br>M<br>b<br>1<br>2<br>12<br>18<br>1<br>3<br>12<br>14<br>22<br>1<br>4<br>12<br>16<br>26<br>2<br>10<br>12<br>14<br>3<br>4<br>8.<br>4<br>5<br>4<br>13<br>16<br>4<br>6 6<br>8<br>10<br>2<br>10<br>Find the most likely time for the process 5<br>given that the critical path time is 37 weeks.<br>9-<br>

Extracted text: Q 2/Draw the PERT network from the given information in the table below: Activity a M b 1 2 12 18 1 3 12 14 22 1 4 12 16 26 2 10 12 14 3 4 8. 4 5 4 13 16 4 6 6 8 10 2 10 Find the most likely time for the process 5 given that the critical path time is 37 weeks. 9-