plz solve it clearly hurry
Extracted text: Q. 2 From the following table, develop network diagram, determine the critical path, and Calculate the minimum duration of project completion. Activity A Predecessor Duration 6. A 4. C A 3. 8. B B 4. F C 6. D.F E G 4 6. F 4 G,H,I