Project Phoenix costs $1.25 million and yields annual cost savings of $300,000 for seven years. The assets involved in the project can be salvaged for $100,000 at the end of the project. Ignoring...



Project Phoenix costs $1.25 million and yields annual cost savings of $300,000 for seven years. The assets involved in the project can be salvaged for $100,000 at the end of the project. Ignoring taxes, what is the payback period for Project Phoenix?




Select one:


a. 4 years

b. 4 years and 1.7 months

c. 4 years and 2 months

d. 4 years and 3 months

e. 5 years




Jun 07, 2022