Project network/schedule activity on node. Prepare a network schedule showing: Early Starts (ES) for all activities Late Starts (LS) for all activities Slacks for all activities Critical path length...




  1. Project network/schedule activity on node. Prepare a network schedule showing:

    1. Early Starts (ES) for all activities

    2. Late Starts (LS) for all activities

    3. Slacks for all activities

    4. Critical path length

    5. Non-critical path length



  2. Schedule Compression

    1. What is the crash cost per day for each activity?

    2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? You may assume that you can partially crash an activity.

    3. What is the new cost after crashing the project?

    4. Is partial crashing an appropriate assumption for this kind of project?




Table 2.1





















































ActivityImmediate PredecessorNormal Time (days)Normal CostCrashed Time (days)Crashed Cost
A - Obtain InstructorNone7$5004$800
B - Locate RoomA3$2002$350
C - Check CoatsNone6$5004$900
D - Room Open?C3$2001$500
E - Schedule ClassB and D2$3001

$550