Project Initiation Instructions The first phase in the project management life cycle is the Project Initiation phase. To begin, you must define the project and identify the objectives, scope, and...

1 answer below »

Project Initiation


Instructions


The first phase in the project management life cycle is the Project Initiation phase. To begin, you must define the project and identify the objectives, scope, and deliverables.


In this assignment, you will:



  1. Select a project scenario to work with throughout the course.

  2. Create a video and PowerPoint presentation in which you:

    • Define the project's objectives, scope, and deliverables in a Project Summary, including a Project Charter and a project management methodology.

    • Create a Work Breakdown Structure (WBS) for the project.




Choose a Project Scenario

Select a case study to use throughout the course to complete the assignments.


Review the parameters for choosing your own case study and for selecting a predetermined case study. Once you have read through the material, decide which you will do.



  1. Destination Wedding: You have been tasked with creating a project to manage a destination wedding. You will be required to figure out the destination. You have been given a budget of $25,000. You will have to determine all costs and resources. The project must be completed in six months.

  2. Data Integration Software Tool for Communications ‘R’ Us Phone Company: You have to build a software tool that enables data to be used by a variety of software applications for a telephone company. The team consists of an unknown quantity of personnel for the design, development, building, deployment, and operation and maintenance of the system. The team members may be located in different time zones. The sponsor, Ted Telee O’Phone, has asked that the tool should also be available in “the Cloud” so that the stakeholders may access it through an Internet browser. The budget for this project is $50,000.

  3. Website for Dee Dee’s Pawn Star Shop: You are leading a team of three individuals to deliver an e-commerce Web site for a small local pawn shop. You are working with a suggested budget of $10,000 to deliver the development of the site, all hardware, and hosting services. The sponsor, Dorothy Deal, would like the site to highlight “Deals of the Day,” as well as items she is looking for to complete collectible collections.

  4. Trip of a Lifetime: You have been asked to plan the trip of a lifetime for a family of four to visit five countries in three weeks with a budget of $35,000. You will need to determine all costs, schedule, and resources for this to be a success.


Create Your Presentation and Deliverables

Create a 5–7-slide PowerPoint presentation with detailed notes. Your presentation should include the following:



  1. Project Summary.

  2. Summary of the Project Charter, including a PM methodology.

  3. Work Breakdown Structure (WBS):

    • Using MS Project or other software, develop a Work Breakdown Structure (WBS) based on your selected business or IT project.

    • WBS should include, at a minimum, four levels.




Use Kaltura to present the PowerPoint and submit a video presentation. Refer to Using Kaltura for directions on recording and/or uploading your presentation in the courseroom.


Note: If you require the use of assistive technology or alternative communication methods to participate in these activities, please contact [email protected] to request accommodations.


Additional Requirements



  • Written communication:Ensure written communication is free of errors that detract from the overall message.

  • Number of resources:Cite at least three current scholarly or professional resources.

  • Length:Create a 5–7 slide PowerPoint with detailed notes.

  • Submission:Submit the video presentation and the PowerPoint slides.

Answered Same DayOct 16, 2021

Answer To: Project Initiation Instructions The first phase in the project management life cycle is the Project...

Deepshikha answered on Oct 18 2021
152 Votes
Project Destination Wedding
Project
Destination
W edding
Project Overview
The idea of this wedding project was conceived to give Paul and Simon, the fantasy wedding that they dreamed of their entire lives.
This project focuses not only on providing the best of destination
wedding experience, but also encompasses a detailed and well strategized project plan in terms of budget, schedule, guest listing, attires, food, wine and most of all fun filled memories.
Utmost care has been taken to consider smallest of details before finalizing on the choice of destination, guest, their accommodations, key milestone planning, budget analysis at specified intervals, quality assurance and proper and timely communication.
Coordination is the key and to maintain proper coordination and transparency a special cloud space has been created. All major bills & documents shall be placed there time to time.
We want to keep a flexible an open approach in accomplishing this project. Thus, the methodology is going to be an integrated approach of both Waterfall and Agile.
Budget is predefined, rest all the factors would be revisited in iterations of 4 weeks to decide upon further course of action.
Project Charter    
Project Summary
Project Management Methodology
Project Budget
In a wedding project, budget plays an intricate role. For this project we have created an elaborate Budget analysis
Key Milestones and deliverables
Time is precious in planning for a wedding and specially a destination wedding. Here are the key milestones defined for this wedding project
Additional Check Items
To make a destination wedding memorable we need to get the following important additional items ticked from our checklist on time and within budget
     Planned Item     Checked
    Rings    
    Attires    
    Music    
    Flower Decorations    
    Guest engagement activities    
    Photographer    
    Return Gifts    


Resource NameTypeInitialsBase% UsageStandard RateCost/UseOvertine RateTotal Cost
BrideWorkBStandard100%$0.00/Hr$0.00/Hr-0
GroomWorkBStandard100%$0.00/Hr$0.00/Hr-0
Wedding Card - 100 GuestsMaterialWCStandard100%101000-1000
Commuting - 100 GuestsCostCmStandard100%201000-2000
Church - BookingCostChStandard100%1500
Property (Hotel Rooms) - 2 daysCostHtlStandard100%4.51000-4500
Banquet HallCostBHStandard100%1500
MusicCostMStandard100%1000
DecorationsCostDcStandard100%2000
Fun ActivitiesCostFAStandard100%1000
Catering - 100 GuestsCostCtStandard100%31000-3000
Wedding Dress MaterialWDStandard100%31000-3000
Wedding RingMaterialWRStandard100%21000-2000
PhotographerCostPhStandard100%1000
Buffer BudgetCost1500
25000
Flat Rate
Flat Rate
Flat Rate
Flat Rate
Flat Rate
Flat Rate
Flat Rate
Work Breakdown Structure (WBS)Duration in DaysStart DateFinish...