Extracted text: PROJEC ILLUSTRATION 8-3 From the following data, perform crashing the project. Cost Cost Time in Weeks Normal Crash Crash 10,000 7,000 3,200 10,0000 5,200 14,000 8,100 9,600 8,000 per week 2,000 Normal 2,000 4,000 2,000 8,000 Activity 1-2-(A) 1-3-(B) 2-4-(C) 3-4-(D) 3-5-(E) 4-6-(F) 5-6-(G) 5-7-(H) 6-7-(i) 600 8 400 7. 4. 500 800 2,000 12 2,000 10,000 6,000 6,000 4,000 7. 3. 700 900 11 1,000 10 6. Total 33 18 P44,000 P75,100 Č=7 F = 3 A = 6 D= 12 G = 5 | = 10 B= 8 E = 7 H = 11 FIGURE 8-5 The normal time Critical Path B-D-F-I is equal to 33 weekS. Direct cost is .....P 44,000 Question: Can we finish the project in 18 weeks instead of 35 weeks at a cost of less than P75,100 in direct cost? SOLUTION: 1. Determine the different path lengths and identify the cine cal path. 190