Progress reports are critical in monitoring progress During the weekly reporting, one person gives the status of an 8-day task as 50% completeand 5 days remaining on the work How many ways could this...

Progress reports are critical in monitoring progress During the weekly reporting, one person gives the status of an 8-day task as 50% completeand 5 days remaining on the work How many ways could this be interpreted and what are the implications of reading it the wrong way?