Consider the following data [Figure].Suppose round robin scheduling is applied on the given data with time quantum=Floor (XX % 3) units. It is also given that scheduling of a process or context switch...


Consider the following data [Figure].
Suppose round robin scheduling is applied on the given data with time quantum=Floor (XX % 3) units. It is also given that scheduling of a process or context switch will take 1 unit of time. What is the completion time and turnaround time of process P4?
Where XX is the last two digits of your roll number.


XX=18


Process No Arrival time Burst time<br>1<br>2<br>3<br>2<br>3<br>1<br>4<br>2<br>4<br>5<br>8<br>5<br>6<br>4<br>

Extracted text: Process No Arrival time Burst time 1 2 3 2 3 1 4 2 4 5 8 5 6 4