Problem (4) The following results have been reported for field pumping test from a well, where the top permeable layer is unconfined and underlain by an impermeable layer, for a steady state...


Problem (4)<br>The following results have been reported for field pumping test from a well, where the top permeable<br>layer is unconfined and underlain by an impermeable layer, for a steady state condition:<br>m3<br>q = 0.68<br>min<br>h, = 5.6m at r, = 60m<br>h, = 5m at r, = 30m<br>Calculate the hydraulic conductivity (cm/s) of the permeable layer.<br>

Extracted text: Problem (4) The following results have been reported for field pumping test from a well, where the top permeable layer is unconfined and underlain by an impermeable layer, for a steady state condition: m3 q = 0.68 min h, = 5.6m at r, = 60m h, = 5m at r, = 30m Calculate the hydraulic conductivity (cm/s) of the permeable layer.