Problem 1. A vertical beam is formed in preparation for concrete placement. The height of the form is 15 ft. The rate of concrete pour rate is 10 ft/hr. and the concrete temperature is 70F. The...


Problem 1. A vertical beam is formed in preparation for concrete placement.<br>The height of the form is 15 ft. The rate of concrete pour rate is 10 ft/hr. and<br>the concrete temperature is 70F. The concrete weighs 150 pcf, contains a<br>retarder, and is made with Type I cement. Draw the pressure envelope for<br>the given conditions.<br>

Extracted text: Problem 1. A vertical beam is formed in preparation for concrete placement. The height of the form is 15 ft. The rate of concrete pour rate is 10 ft/hr. and the concrete temperature is 70F. The concrete weighs 150 pcf, contains a retarder, and is made with Type I cement. Draw the pressure envelope for the given conditions.