The following table shows activities with duration, dependency, dependency type, and the number of workers from one small segment of a project network. Draw the segment of the network diagram and then: (a) Show the resource usage (chart) if activities A, B, and C start on day one; (b) Show the new network diagram and the resource usage (chart) when resources are leveled after applying appropriate slack times.
Extracted text: Predecessor Number of Dependency Туре Activity Duration (dependency) Workers A 2 D 2 B 4 D 2 10 M 4 3 А D 2 E 1 В D 2 F 2 C,D,E M(C,E) 4