Please write the working steps solutions in a Microsoft Word document and show how you get the answer each of the question below 1-13.1-You have a project worth $400,000. Four months have...

1 answer below »

View more »
Answered Same DayNov 26, 2022

Answer To: Please write the working steps solutions in a Microsoft Word document and show how you get the...

Prince answered on Nov 26 2022
58 Votes
1-You have a project worth $400,000. Four months have passed and $200,000 has been spent. Upon closer review, you findthat only 30% of the work is completed; however, as per the schedule, 40% of the work should have been completed. Determine the Schedule Performance Index (SPI) and CPI. Comment on the project performance.
Group of answer choices
· CPI = 1.6, SPI = 1.75, Under Budget and Ahead of Schedule
· CPI = 0.6, SPI = 0.75, Over Budget and Behind Schedule
· CPI = 0.8, SPI = 0.85, Over Budget and Behind Schedule
· CPI = 0.6, SPI = 0.75, Under Budget and Ahead of Schedule
Solution:
Project Cost = $400,000
Actual Cost = $200,000
Actual Value = 30%*40000 = $120000
PV = 40% * $400,000 = $160,000
CPI = $120,000/$200,000 = 0.6
SPI = $120,000/$160,000 = 0.75
Since, CPI is less than 1, it is over budget and SPI is less than 1, it is behind Schedule.
So, Correct Solution is Option is CPI = 0.6, SPI = 0.75, Over Budget and Behind Schedule
2- You have a project to be completed in 12 months, and the cost of the project is 220,000 USD. Six months have passed, and 100,000 USD has been spent, but on closer review, you find that only 40% of the work has been completed so far. Find the Estimate at Completion (EAC) for this project.
Group of answer choices
· $250,000
· $150,000
· $125,000
· $225,000
Solution: CPI = (220,000 * 40%)/100,000 = 0.88
BAC = 220,000
EAC = 220,000/0.88 = $250000
Correct Option is $250,000
3- You have a fixed deadline project with a budgeted cost of 600,000 USD. So far you have spent 400,000 USD and the value of the completed work is 375,000 USD. However, as per the schedule, you should have earned 425,000 USD to date. Calculate the Estimate at Completion (EAC) .Hint: While computing CPI and SPI, try to retain four decimal places.
Group of answer choices
· $455,000
· $432,034.82
· $672,001.93
· $632,034.82
Solution: CPI = 375000/400,000 = 0.9375
SPI = 375000/425,000 = 0.8823
BAC = 600,000
EAC = AC + {(BAC – EV)/(CPI*SPI)} = 400000 + (600000 – 375000)/(0.9375 * 0.8823) = $672,001.93
Correct Option is $672,001.93
4- You are working on a project to be completed in 24 months and the total cost of the project is $220,000. Twelve months have passed and 100,000$has been spent, and 60% of the work has been completed so far. What is the TCPI?
Group...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30