please select the social project first and confirm with me and then proceed further

1 answer below »

View more »
Answered 7 days AfterJun 02, 2022Curtin University

Answer To: please select the social project first and confirm with me and then proceed further

Dr Raghunandan G answered on Jun 07 2022
83 Votes
1. Introduction (25%)
A. Executive Summary: It is discussed both the financial risk of constructing a substation as well as a model for assessing the financial risk of constructing a substation that is based on Monte Carlo simulation. At first, they presented the evaluation index of marriage function social project financial risk assessment and performed an analysis of the primary risk elements in marriage function social project financial risk assessment. The marriage function social project financial risk assessment model that is based on Monte Carlo simulation was built on the basis of this. After that, the validated model was utilized to conduct a financial
risk assessment on a marriage function social project. With a budget of the project are 34090 dollars, the wedding and reception will be accomplished. As available resources and estimated costs for contractual operations become available, the prices will be revised progressively. Quality. The ceremony will be prepared in accordance with the Bride and Groom's wishes. The Bride and Groom must examine all deliveries before they will be locked for the wedding or celebration.
Justification of Probability Distribution for One Cost Variable The Bride, Groom, and PM are accountable for managing. The aim is for the Bride and Groom to appreciate their wedding reception, leaving them with positive memories to last a lifetime.
    Name
    Role
    Authority
    Person A
    Scope Statement / Final approval
    Commitments: Following the approval and completion of a project. The acquisition of cash resources.
    Person B
    Product Owner / Review and approval Charters
    Responsibilities:
Quality assurance and delivery of the project. The acquisition of funds. Confirm any modifications or repairs that need to be made.
    Person C
    Review and approval Contract / Development Manager
    Coordination of all sections of the process is one of your tasks. Ensuring that projects are performed on schedule and within budget. Partners should be updated on the project's progress, and any risks should be identified. Organize contractors to guarantee that the job is completed correctly.
Authority: Extended warranty discussions. Such concerns should be discussed only with parties.
1. The Bride does not already have most of the necessary finances to finish the job.
2. By June 6,2023, the project should be done.
3. The average cost will not exceed $34090.
4. There must be no more than 250 people on the invite list.
The following are key presumptions:
The following are key presumptions:
2. The Bride and Groom will not cancel their wedding plans.
3. Now the project will be finished by June 6,2023 for a total cost of $34090.
The project team is the group organizing wedding and celebration. The objective is to finish the wedding according to the couple's wishes and offer people with a strain and pleasurable experience.
Wedding Components and Steps:
· Apparel
· Reception Venue
· Music
· Printing
· Photography
· Decorations
· Flowers
· Gifts
· Travel
· Others
B Recommended Baseline Budget
The measurement of probability in risk management frequently makes use of probability distributions. It also calculates the total amount of loss that will be sustained by an investment portfolio based on a distribution of the returns that have been experienced in the past. One common statistic used in investment risk management is known as the Value-at-Risk. A flexible budget is a cost of doing business that fluctuates depending on how far the company develops or spreads its products or services. This type of cost of doing business is also known as a cost of doing business that is variable. When there is a decline in the output price, indirect expenses go up; when there is a rise in the output price, indirect expenses go down. Indirect expenses go up when there is a dip in the purchasing and selling demand within an industry. In spite of the fact that the information on uncertainties and associated attributes, such as higher or lower values, ranges of quantities, and prospective costs, cannot be easily taken into consideration, this information can either be calculated or is easily accessible to the general public. In other words, this information can be taken into account. A predictable estimation in the perspective of risks is one that is based on a single numerical value. It should not take into consideration the parameter's order to assess the effects or chance of recurrence. The benchmark budget is used as a comparison in cost estimating to evaluate projected and true expenses. It provides the organization ’s ability to assess the program's performance indicators. This will be impossible to conduct corrective and preventative steps if the benchmark is not established. The cost is compared to a cost estimate, and it is component of project planning phase. Funding takes place early on, but spending guidelines are a cost-effective way to monitor success during installation(L. Bertot, S. Genaud 2018).In this example we have considered total expenses to be 34090 dollars and the actual cost estimate was 18099 dollars. Hence the overlay of this project is 15991 dollars. A statistical graph was plotted and theoretical and statistical values were noted. Individual expense graph was plotted using the details discussed [7].
    Apparel (in dollars)
    Category
    Deterministic Estimate
    Probabilistic Approach
    Over/Under
    Fiancé 1 gown
    3,000.
    2,500
    50
    Fiancé 1 shoes
    3,000
    300
    2,700
    Fiancé 2 ring
    300
    250
    50
    Fiancé 2 shoes
    200
    175
    25
    ring(s)
    10,000
    1,500
    500
    Fiancé 1 headpiece
    500
    500
    0
    Fiancé 1 hosiery
    500
    20
    480
    Fiancé 2 veil/headpiece
    500
    500
    650
    Fiancé 2 hosiery
    500
    1,000
    -500
    Fiancé 2 gown/tuxedo
    1,000
    350
    -500
    Fiancé 1 jewelry
    4,000
    550
    3,450
    Fiancé 2 jewelry
    400
    550
    -150
    Fiancé 1 ring
    2,000
    2,300
    2,700
    Apparel Total
    25,900
    10,495
    9,455
    Category
    Deterministic Estimate
    Probabilistic Approach
    Over/Under
    Room/hall fees
    250
    150
    100
    Tables and chairs
    100
    50
    50
    Food
    0
    0
    0
    Linens
    0
    0
    0
    Cake
    700
    700
    0
    Favors
    50
    28
    22
    Staff
    0
    0
    0
    Reception Total
    1,100
    928
    172
2. Explanation of Two Risk Events
· Unsystematic risk, sometimes referred to as business risk, is a form of risk associated with this particular event. Unsystematic risk, also known as potential losses, can be reduced via diversification. Unsystematic risk with systematic risk represents the overall danger.
· Investment strategy risk that is not contingent on money invested and is attributed to broad market factors is referred to as...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30