ASSESSMENT TASK 3: PROJECT TROUBLE-SHOOTING QUESTIONS: Task summary: Be sure to be thorough and detailed in your responses. (One-line responses will be failed!) Reflect on your training...

1 answer below »
Please Question task file and instruction file


ASSESSMENT TASK 3: PROJECT TROUBLE-SHOOTING QUESTIONS: Task summary: Be sure to be thorough and detailed in your responses. (One-line responses will be failed!) Reflect on your training modules/PowerPoints on Canvas as needed to complete. No referencing is required as this is to be YOUR OWN WORDS and description of actions that YOU would take. Answer the question in the spaces provided. Save your file and upload with cover sheet to Canvas. QUESTION 1) Tuesday WEEK 1 OF PROJECT You are having issues with the suppliers of the selected countertops for the Café being able to confirm their delivery time… a) What do you do? b) How do you avoid this impacting the project timeline? QUESTION 2) Thursday WEEK 1 OF PROJECT The plumbers have failed to seal the sink in the back storeroom, and it is leaking across the newly laid tiles. a) Outline the steps you would take to manage this situation: b) What are the possible implications of this? c) How will you manage the possible issues raised in part b) QUESTION 3) Friday of WEEK 1 OF PROJECT The water leak that occurred in question 2 has affected the wiring in the café and has caused all the electrical outlets to short circuit. a) Outline the steps you would take to manage this situation: b) How would you accommodate the additional costs that fixing the electrical issues have raised? Who would you contact in relation to this? QUESTION 4) Thursday WEEK 2 OF PROJECT The Owner of the Café has come in contact with Covid-19 by travelling and is required to isolate for 14 days. Therefore, she will be unable to visit the site daily, as has been her routine so far. a) How as her appointed Project Manager will you keep her across everything adequately? b) What types of information would you report to her and how often? QUESTION 5) Monday WEEK 4 OF PROJECT There has been a fire in the marketplace where the Café is located. The building has been evacuated whilst ACT Fire Brigade attend the scene. There is no direct damage or danger to the Café. However, as no contractors can continue working until the building is deemed safe - this causes you to lose valuable time on your project timeline. a) How do you adjust your plans for this unexpected incident? b) What type of discussions would had with the subcontractors in relation to making up the time lost? 2 ASSESSMENT TASK 3: PROJECT TROUBLE-SHOOTING Task summary: You are the Project Manager of THE CUPNBAKE Project as per assessment 1 & 2. In this assessment you will be required to answer specific trouble shooting questions in detail in relation to the project. Be sure to be thorough and detailed in your responses. (One-line responses will be failed!) Reflect on your training modules/PowerPoints on Canvas as needed to complete. No referencing is required as this is to be YOUR OWN WORDS and description of actions that YOU would take. Answer the question in the spaces provided. Save your file and upload with cover sheet to Canvas. What do I need in order to complete this assessment? Computer and Microsoft Office Access to the Internet for research Access to your learning materials When do I do this task? This task may be done in your own time DUE DATE IS: Sunday 14th March @ 11:59pm. What do I need to SUBMIT: · Completed Project Troubleshooting Questions – use template · Assessment Cover Sheet What do I need to do if I get something wrong? If your assessor sees that you have not completed all parts of the task completely and satisfactorily, the details of resubmission will be outlined to you through the Canvas LMS through assessment feedback. Templates provided: · Question Template HERE: · · Assessment Cover Sheet HERE: · · Task outline (same as this information) HERE: · (Please check your downloads folder for the template if it does not open straight away) BSBPMG522 Undertake project work_2021 Capital Collegewww.capital.edu.au
Answered Same DayMar 12, 2021BSBWOR501Training.Gov.Au

Answer To: ASSESSMENT TASK 3: PROJECT TROUBLE-SHOOTING QUESTIONS: Task summary: Be sure to be thorough and...

Tanmoy answered on Mar 13 2021
156 Votes
ASSESSMENT TASK 3:PROJECT TROUBLE-SHOOTING QUESTIONS:
Task summary:
Be sure to be thorough and detailed in your responses. (One-line responses will be failed!)
Reflect on your training mod
ules/PowerPoints on Canvas as needed to complete.
No referencing is required as this is to be YOUR OWN WORDS and description of actions that YOU would take.
Answer the question in the spaces provided. Save your file and upload with cover sheet to Canvas.
    QUESTION 1) Tuesday WEEK 1 OF PROJECT
You are having issues with the suppliers of the selected countertops for the Café being able to confirm their delivery time…
a) What do you do?
· First we must select domestic suppliers which will minimize the lead time by two weeks or more;
· Ordering in smaller quantities by reducing the longer lead times and reducing the carrying costs;
· Let the suppliers know the reorders expected based on the actual sales forecast.
· Spend less time on customised products and emphasize the suppliers for the standard components (John Sharman, 2019).
b) How do you avoid this impacting the project timeline?
1. Setting realistic goals for the project and working as per the schedule
2. Holding a team meeting and allowing the team to communicate their vision towards the project.
3. It needs to be analysed whether the budgeted amount can cover the cost of project and help in additional funding
4. Dividing the individual tasks and works into various phases, establish the reliance, sequence the activities and estimate the required resources and timeline of each tasks.
5. Tracking and measuring the progress of the goals is important
6. Finally, it ends with forecasting by considering the present stock status and extrapolating with the available data in order to determine the future results at the project’s end (Project, 2020).
    QUESTION 2) Thursday WEEK 1 OF PROJECT
The plumbers have failed to seal the...