ORANGE COUNTY FINANCIAL CASE-Value At Risk Calculations Please complete the project by using the information in the attached excel file below: Required: 1. Use the excel file to compute the following...

1 answer below »

View more »
Answered Same DayNov 04, 2021

Answer To: ORANGE COUNTY FINANCIAL CASE-Value At Risk Calculations Please complete the project by using the...

Himanshu answered on Nov 05 2021
152 Votes
Section: 1 Duration Approximation
Bond value = 7.5 billion dollars
Effective Duration = 7.4 years
Medium Maturity bond with rate 5.2%
Rates: Increased by 3%
The duration of a bond is a
linear approximation of minus the percentage change in its price given a 100-basis point change in interest rates. (100 basis points = 1% = 0.01) (ProfessorCarpenter, n.d.)
Answer-1
The predicted loss can be approximated using the modified duration approximation for annual compounding:
ΔB = -(DBΔy)/(1+y)
= - {(7.4) (7.5) (0.03)/ (1.0515)}
= -1.5835 billion dollars which is very close to the actual loss of 1.64 billion dollars.
Whereas,
ΔB = Predicted loss
D= Duration of the Bond = 7.4 years
B = Amount invested = 7.5 billion
ΔY = increased rate 3%
Y = Yield = 5.15
{Note: We have used January 1994 yield, y in the denominator}
Section: 2 Computation of portfolio Var
Answer-2 Delta Normal Distribution
We have been given 5 Year yield data of the bond with the help of this data we have calculated the monthly rate of return of the portfolio which gives the Mean of 0.09% and Standard deviation of 0.049 Approx. As given, we need to calculate Value at risk at a confidence level of 95% level. We have used excel formula NORMINV at bottom of 5% and we get -7.97% which suggests annual investment will lose only almost 8 % of the amount not more than that. As per the Var. For the monthly assessment, we need to divide the annual figure with SQRT (1/12). Monthly value at risk at confidence level 95% is equal to $ 174 million approx.
Answer-3 Historical Simulation Method
As per the methodology, we need to first count all the numbers we have used the count excel formula to get the total number of observations after that as per the 95% confidence level or bottom 5% we calculate the risk value. As there were 60 observations in the data of 5-year yield so the bottom 5% level comes out to be 3 which...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30