PROJ6003 Project Execution and Control Assessment Case Study 2021 1 * The contents of this Case Study were adapted from a real case to suit the requirements of the PROJ6003 subject’s assessments and...

1 answer below »
Please ensure the assessment should be based upon the attached case study and referencing should be done in APA 6 with intext citation.


PROJ6003 Project Execution and Control Assessment Case Study 2021 1 * The contents of this Case Study were adapted from a real case to suit the requirements of the PROJ6003 subject’s assessments and are the property of Torrens University Australia. Department Asset Management System – DAMS Project Background The organisation is a large state-based government department in Victoria with assets and stakeholders throughout the entire state of Victoria. This project is to deliver an Asset Management Information System which will store the details of all new and existing assets, which include land and buildings across multiple locations. We will call the system DAMS, Departmental Asset Management System. The DAMS System replaces over 20 department asset management systems and manual processes, including systems written in MS Access, Excel and Lotus Notes. Due to the number of assets and divisions within the department, it was decided that the system would be developed and deployed over a three-year period, with three separate deployments. The project was purchased on the basis of responses to a tender, and the successful supplier was an experienced vendor, who had previously delivered this application to other state government-based agencies. We will call the vendor Great IT Systems (GIS). The contract was approved as a fixed price contract, using the Requirements Specification document from the Tender as the agreed basis for costing. The contract allows for changes to specifications and requirements at a fixed hourly rate according to the rate card. The CoTS (Commerical Off the Shelf) software solution was purchased for a cost of $5.5M plus implementation and training costs. Training development and delivery was quoted at a cost of 500 days at a daily rate of $1000 per day. Implementation costs, including requirements analysis, customisation and system testing were charged at $3M. Hardware and infrastructure was purchased at a cost of $4.5M. Total cost of the project is recorded as lifecycle cost, whick includes ongoing maintenance during the life of the program, generally made up of the initial contract plus two extensions of the initial contract. Changes and additions to scope are based on the rate card (Appendix 1) The initial intention was that the selected application would be implemented as it was, out of the box and with minimal customisation. The business users would need to change their ways of working to follow the processes that are introduced via DAMS. Project Team The current vendor Project Manager has successfully delivered many projects and is well known for her Stakeholder Management and Project Delivery skills. We will call her Lee. The current department Program Manager is a consultant with many years of experience, but has only recently joined the department on a contract basis, specifically to deliver the DAMS Program. We will call him Mark. Glenn is a Project Manager, who reports to Mark, and has also joined as a consultant. Glenn has worked with this department previously as a consultant, and has delivered a number of applications, including AssetMan which will now be replaced by DAMS. A Business Analyst has also been allocated to the Program. He comes from within this government department and has worked in an IT delivery role for six years, He too has implemented AssetMan and knows Glenn well. We will call him Martin. Recently, a Project Officer, Teena, has joined the Project Team. Her role is to schedule and manage meetings and training dates. Teena is an experienced Project Manager who has worked for many government organisations and understands how to communicate effectively with the key PROJ6003 Project Execution and Control Assessment Case Study 2021 2 * The contents of this Case Study were adapted from a real case to suit the requirements of the PROJ6003 subject’s assessments and are the property of Torrens University Australia. stakeholders. Teena is present in all meetings and in all training sessions. Teena feels that she is underutilised and that Mark is not taking advantage of her skillset. She also feels that Lee is using her as the scapegoat for any issues that are coming to light. Teena is not included in the Project Steering Committee Meetings, which frustrates her, as most of the Project Team and stakeholders come to her first with any questions or problems. The organisation has allocated Subject Matter Experts to the Program, with the expectation that the solution will satisfy all of their needs, and that all staff will use the full system once it has been delivered. The Subject Matter Expersts are specialists in their area of work, with a number of stakeholders allocated to a super user role. This role allows them to create new users, and update new code tables according to the needs of the teams and applications. The key internal stakeholders, especially the Subject Matter Experts, who have been seconded to the Project Team, have worked in their role and team for many years, and are very experienced in their current applications. They do not understand the roles or needs of other teams and really are not interested in knowing what the others do or how they do it. They do not understand why they need to use an application that takes into consideration the needs of the other teams. The benefits of implementing DAMS are not immediately visible to these internal stakeholders, who believe that the new systems are imposing more work on them, rather than simplifying the processes. A number of Subject Matter Experts, who have been seconded to the Project Team, do not have a long-term view of the needs of their team, but rather have a limited view based on what they currently do. The application requirements have been developed on the basis of information gathered from these Subject Matter Experts. PROJ6003 Project Execution and Control Assessment Case Study 2021 3 * The contents of this Case Study were adapted from a real case to suit the requirements of the PROJ6003 subject’s assessments and are the property of Torrens University Australia. Figure 1 Program Organisational Structure Corporate and Branch teams The Staff, who are located at Head Office within their corporate teams, are primarily responsible for liaising and supporting the branch office staff, however they are mainly called upon to report on KPIs and ensure that the projects which are created for each branch office, are delivered according to agreed requirements. For the purposes of simplicity this report will focus on the impacted divisions within the Corporate Head Office location, along with their branches which are located in Metropolitan and Non-Metropolitan Regions across the state. The Branch staff are responsible for their assets and their staff as well as their own customers. The Branches are the delivery arm of the department. While they manage assets and maintenance work at their own sites, they are also responsible for the delivery of the department services to their local communities. These Branch staff are also responsible for reporting back to the Corporate Divisions. The aim of DAMS is to reduce the amount of duplication in the preparation of these reports for the Corporate teams, using the data from a centralised base of information, which can be accessed, depending on securities and permission, by all staff who need to access the data. PROJ6003 Project Execution and Control Assessment Case Study 2021 4 * The contents of this Case Study were adapted from a real case to suit the requirements of the PROJ6003 subject’s assessments and are the property of Torrens University Australia. The Corporate and Branch teams and their applications within DAMS are listed below in Table 1 Division and Applications. The Regional structure is shown in the map below in Figure 2 Regional Divisions within Victoria Table 1 Division and Applications Corporate Division / Branch Responsibility Application Release date Asset Management Asset Register Release 1 – deployed Agreements Release 1 – deployed Disposals Release 1 – deployed Acquisitions Release 1 – deployed People and Culture People and Lists Release 1 – deployed Corporate Finance / All branches Contractors Release 1 – deployed Corporate Finance Investment Management Release 3 – no release date Capital Allocation Tool Release 3 – no release date Corporate Reporting Reporting Release 1 – deployed Forecasting and Modelling Release 3 – no release date Corporate Planning Asset Management Planning Modelling Release 3 – no release date Corporate Planning / All branches Condition and efficiency management Release 3 – no release date Asset Management Reform Implementation Team / All branches Property Condition Evaluation Release 2 - delayed Capability Building Unit/ All branches Asset Maintenance Plan Release 2 - delayed Corporate ESM Team / All branches Essential Safety Measures Release 2 - delayed Response Programs Unit / All branches Asbestos Registers Release 2 - delayed Safe Program Release 2 – delayed Asbestos Management and Audits Moved to Release 3 Cleaning Unit / All branches Cleaning Release 2 – delayed, part has been moved to Release 3 PROJ6003 Project Execution and Control Assessment Case Study 2021 5 * The contents of this Case Study were adapted from a real case to suit the requirements of the PROJ6003 subject’s assessments and are the property of Torrens University Australia. Corporate Division / Branch Responsibility Application Release date Contractor Panel application and management Release 3 – no release date Cleaning Audits Release 3 – no release date All branches Work Order Management Release 2 - delayed Figure 2 Regional Divisions within Victoria The product The key benefits of DAMS are mainly aimed at the Corporate Management Teams, who are looking at the centralised reporting and centralised future planning options which will be delivered when the project has been completed. Several applications scheduled for Release 3 are aimed at achieving the future planning requirements. At this completion of Release 3, all of the applications will have been delivered and all staff, state-wide, will have been trained with some havingused the applications for at least 12 months. The Corporate Reporting Team will be developing key reports to provide planning and modelling for future asset acquisitions and asset maintenance programs. These reports will feed future budget proposals which will be submitted to
Answered 4 days AfterJun 16, 2021PROJ 6003

Answer To: PROJ6003 Project Execution and Control Assessment Case Study 2021 1 * The contents of this Case...

Udit answered on Jun 20 2021
146 Votes
PROJ6003: PROJECT EXECUTION AND CONTROL.
Table of Contents
Executive Summary:    3
INTRODUCTION:    3
Identification of Change:    3
Impact on Scope, Time, Cost and Quality:    4
Tools and techniques used to manage change:    5
Change Request:    6
Satisfaction of proposed change and risk associated with it:    7
Conclusion:    7
References:    8
Appendix:    10
Change request form (CRF):    10
Executive Summary:
Department Asset management software is expected to be adopted in the organisation, and considering the entire case study, a change is proposed. T
he proposed change focussed on reducing the cost and time, and various tools and techniques have been analysed regarding its change. Tools such as flowcharts, ADKAR analysis, culture mapping etc., have been used to manage change throughout its process. Analysis of the impact of change on scope, time, cost, quality has also been done. A short discussion about the steps involved in change management has also been made. The initial process is to identify the scope of change, the influence of the change within the organisation, the approval of all departments, and the communication of such change to the stakeholders. Formulating a written communication procedure through a traditional medium has also been discussed in terms of scope and time. It broadens the scope and saves time for the organisation by preventing documenting every task given by top officials from time to time.
INTRODUCTION:
Department asset management system is software used to keep track of hardware devices, inventories, software, and other assets of the organisation. This system notes down all records that have happened to occur from acquisition to its disposal of assets. The study suggests implementing the asset management system in the organisation so that assets can be effectively maintained. It will also pay attention to bringing up new technologies in the organisation with obsoleting the old method of asset management, bringing a massive change in the asset management ways. This study will show the way as to how a proposed change can impact different factors like cost, quality, scope, and time. This study shall focus on proposing a change in the current case study and adopting different tools and techniques that should be used while implementing change. We shall also discuss how the change process implements in an organisation and other elaborate different strategies required to adopt the change and associated risk.
Identification of Change:
Department asset management system performs the role of evolving, operating, supporting and disposing of assets in a cost-effective method. An asset management system's presence helps an organisation keep track of all its assets, whether liquid or fixed. It enables it to keep accounts for all of its assets and their utilisation and any changes (Rosenbaum, More & Steane, 2018). The proposed change is providing training to the people for changing and evolution of the corporate attitude. Training is necessary to provide to all the needy employees. They do not have adequate information about the new asset management system that was going to introduce. Also, necessary information about anything can be conveyed easily between the subordinates and its top officials. For implementing change, tools such as ADKAR analysis was used, which ensures team leaders achieve and earn the support of their employees so that the change in strategy can effectively (Mathar & Gaur, 2020). Five steps need to be fulfilled, the first being spreading awareness among the employees about the change that was occurring and why the employees are expected to attend the training program to be well informed about the newly introduced system. The second step would be to persuade and inspire the employees to support the change that is their part in general rather than forcing them. The third step is to impart knowledge about the usage of the system through various training programs, tutorials. The fourth step would be to improve the employees' ability by providing them continuous feedback and evaluating the problems they faced in the program (Jayatilleke & Lai, 2018). The last and final step would be to ensure that old methods are not adopted again and new department asset management system methods are adopted. The employer can do this by giving incentives and promotional offers to employees. 
Impact on Scope, Time, Cost and Quality:
When the matter is related to project management, these four factors like cost, quality, time, and scope play an essential parameter. 
· Time
With change required in training for changing the corporate attitude, people may be reluctant, which can reduce the speed of the work, but in the later phase, the time taken for approval will be reduced. By formulating the procedure of written communication through traditional mediums will increase the processing time and will lead to time consumption (Thakur & Mangla, 2019). Adopting some process apart from the standardised procedures will increase the time of the whole process because of the shortcuts that the standardised procedure may eliminate. 
· Scope
Adequate training for improving the corporate attitude will increase the scope of work for the Departmental asset management system (Tang, 2018). Moreover, it will lead to helping conflict management and the value of time. Formulating a method of adopting written communication through traditional mediums will...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here