PI Planning is several weeks away. Product Management wants to define
the list and number of features that are likely to be planned by the train in the upcoming planning meeting.The RTE should coach the Product Manager to use which option as the denominator of WSJF calculation? -Job size based on relative estimation by the stakeholders -The number of features in the backlog -A relative (Fibonacci) number estimated by the Business Owners -An absolute number of story points estimated by development teams working on the current PIWhich answer is right ? I assume 4.Not 1 because stakeholders should not estimate.Not 3 because Business Owners should not estimate.I doubt on 2. Why should I not choose 2 ? Explain please. Thank you.