PERT Calculations yield a project length of 45 weeks with a variance of 12.25. The project is expected to complete with a probability of 90% in how many weeks.(Round off to next higher integer) 1.1...

Solve in 10 min pleasePERT Calculations yield a project length of 45 weeks with a variance of 12.25. The project is<br>expected to complete with a probability of 90% in how many weeks.(Round off to next higher<br>integer)<br>1.1<br>1.2<br>1.3<br>Probability<br>86.43<br>88.49<br>90,32<br>Use above table for linear interpolation.<br>50<br>O 51<br>52<br>53<br>

Extracted text: PERT Calculations yield a project length of 45 weeks with a variance of 12.25. The project is expected to complete with a probability of 90% in how many weeks.(Round off to next higher integer) 1.1 1.2 1.3 Probability 86.43 88.49 90,32 Use above table for linear interpolation. 50 O 51 52 53