Percentage of Completion is favored to be used under the following circumstances, except: a. Progress Billings is assured of collection b. Performance obligation can be reliably measured c. Contract...





Percentage of Completion is favored to be used under the following circumstances, except:















a. Progress Billings is assured of collection







b. Performance obligation can be reliably measured







c. Contract Price is assured







d. Contract Costs can be reliably estimated