ou have signed a contract to build a garage for the Simpsons. You
will receive a $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days.Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?IDDescriptionPredecessorTime (days)APrepare SiteNone2BPour FoundationA3CErect FrameB4DRoofC4EWindowsC1FDoorsC1GElectricalC3HRough-in FrameD, E, F, G2IDoor OpenerF, G1JPaintH, I2KCleanupJ1