One way of interpreting an SPI of .95 is the project_______. It is a fill in the blank question and maybe I am just drawing a blank but this not making a lot of sense to me. I know a SPI is Schedule...




One way of interpreting an SPI of .95 is the project_______.


It is a fill in the blank question and maybe I am just drawing a blank but this not making a lot of sense to me. I know a SPI is Schedule Performance Index, the ratio of performed to scheduled work; and that it is calculated as EV/PV (earned value/planned value.)


My thought is that this is the projects completion rate, would this be correct?




Dec 07, 2021
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here