Extracted text: On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which The is estimated cost P31,200,000. company recognizes construction to Data on this project for 2022-2024 follow: Est'd Costs revenue over time. Contract Costs Billings 10,500,000 12,500,000 14,440,000 incurred to Complete 20,540,000 13,156,000 2022 5,460,000 9,984,000 2023 2024 15,756,000 The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. contract was delayed for 8 weeks In 2024, the What is the gross profit for 2024? 1,164,000 1,466,400 1,724,000 1,824,000 А. с. в. D.