On average, the manufacturing (processing) time spent per order is approximately 4 days. In addition, a typical order spends 4 days moving from process to process, 3 days in storage, and 2 days in...


On average, the manufacturing (processing) time spent per order is approximately 4 days. In addition, a typical order spends 4 days moving from process to process, 3 days in storage, and 2 days in inspection. For an average order, what is the manufacturing cycle efficiency (%), rounded to 1 decimal place (e.g., 32.463% = 32.5%)? (Hint: Refer to Exhibit 14.14 and accompanying discussion.)