Neelopak Berhad prepared the standard cost data for one of their products.Direct Labour (0.65 hours @ RM11) RM7.15Direct Materials (5 meters @ RM5) RM25Variable Overhead (0.65 hours @ RM7) RM4.55Fixed Overhead (0.65 hours @ RM3) RM1.95Standard cost per unit RM38.65There is the actual cost data information:Production 7,500 unitDirect materials used (23500 meter) RM124,550Direct materials purchasing (24,000 meter) RM132,000Direct labor (3000 hours) RM34,500Variable overhead RM21,600Fixed overhead RM7,800Budgeted activities are 2,600 hours.You are required to calculate:i) Variance of direct materials priceii) Variance of direct materials usediii) Variance of direct labor charge rateiv) Variance of direct labors’ efficiencyv) Variance of variable overhead expensesvi) Variance of variable overhead’s efficiencyvii) Variance of fixed overhead expensesviii) Variance of fixed overhead volume