MITS5001 Assignment 2 MITS5001 IT Project Management Research Report July 2019 MITS5001 Assignment 2 Copyright © XXXXXXXXXXVIT, All Rights Reserved. 2 Research Report (Individual Assignment) - 10%...

1 answer below »

View more »
Answered Same DaySep 27, 2021MITS5001

Answer To: MITS5001 Assignment 2 MITS5001 IT Project Management Research Report July 2019 MITS5001 Assignment 2...

Priyanka answered on Sep 30 2021
161 Votes
Introduction
The report focuses on an analysis of project time management and project risk management based on the utility function. Typically, a business focuses on risk analysis based on cost. The report highlights the dimension of time as well to meet the deadline for the projects. In some projects sometime
s, project time management is more important than project risk management or non-completion of the project on time is capable of increasing costs. The article is overlapping boundaries of the project time management and project risk management. The report goes beyond methodologies of risk analysis in monetary terms.
Body of the report
The boundaries of project risk management and project time management overlap and it is a very special case of risk management. The reason for treating it especially is because sometimes for some projects, the prompt achievement of the projects is very important. The risks in the project management are always certain and they occur in almost every project. Create a negative effect on the achievement of the objectives of the project. The opposite of it is called positive opportunities. Risk management provides strategies for controlling risk.
Time management is very crucial and one of the very important functions in project management and it includes elements like sequence, resources, durations, development and control of the schedule. Sequencing is a process of recognizing the relationships that take place between the activities of the project. In the second step of resources, it is important to understand the estimate of the quantities and type of raw material, types of equipment, human resources, necessary supplies for the performance of every activity. The process of duration involves the activities to be done individually with the help of resources. Development of schedule is a process of analysis of sequences of the activities, duration required, necessary resources and the constraints in the schedule. Control of the schedule is the step the monitor the status of the activities to find out the progress of the project and management of the changes according to the baseline of the schedule.
Cardinal utility function
The utility function is of two types: Cardinal and ordinal. Cardinal utility function is better over time and ordinal utility function takes care of only the ranking and not the strength of the priorities. An example of Cardinal utility is the possibility of attaining the target of the project that is multiplied with its value and then subtracted with the costs that are involved in its execution.
Milestones of soft and hard deadlines
According to the conditions of the contract in large, the provisions to deal with the delay of the projects are always present. The provisions are often related to the penalties. If the deadline is crossed and the project is not suffering any penalty, this may also be called a soft deadline. If a project is submitted after crossing the hard deadline also then it is referred to as costly or of no use. It not only brings the loss because of the delay in execution but it also causes...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30