Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 6,000 units of product...


Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 6,000 units of product were as follows:





















































Standard Costs

Actual Costs
Direct materials7,800 lb. at $5.907,700 lb. at $5.80
Direct labor1,500 hrs. at $16.101,530 hrs. at $16.40
Factory overheadRates per direct labor hr.,
based on 100% of normal
capacity of 1,560 direct
labor hrs.:
Variable cost, $3.00$4,460 variable cost
Fixed cost, $4.70$7,332 fixed cost

Each unit requires 0.25 hour of direct labor.



Required:<br>a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.<br>Direct materials price variance<br>Direct materials quantity variance<br>Total direct materials cost variance<br>b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.<br>Direct labor rate variance<br>Direct labor time variance<br>Total direct labor cost variance<br>c. Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as<br>a positive number.<br>Variable factory overhead controllable variance<br>Fixed factory overhead volume variance<br>Total factory overhead cost variance<br>

Extracted text: Required: a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Direct materials price variance Direct materials quantity variance Total direct materials cost variance b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Direct labor rate variance Direct labor time variance Total direct labor cost variance c. Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Variable factory overhead controllable variance Fixed factory overhead volume variance Total factory overhead cost variance

Jun 01, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here