Machine hours and electricity costs for Wells Industries for 2011 were as follows:
Machine
Electricity
Month
Hours
Costs
January
2,000
$ 9,200
February
2,320
10,500
March
1,520
6,750
April
2,480
11,500
May
3,040
14,125
June
2,640
11,000
July
3,280
12,375
August
2,800
11,375
September
1,600
7,750
October
2,960
13,000
November
3,760
15,500
December
3,360
13,875
Required:
A.
Using thehigh-low method, develop an estimate ofvariableelectricity costs per machine hour.
______________________________
B.
Using thehigh-low method, develop an estimate offixedelectricity costs per month.
C.
Using the high-low method, develop acost function (linear cost equation)for use in
estimating monthly electricity costs.
D.
Using thecost equationyou developed in “C” above, estimate thetotal electricity costs
for a month in which3,000 machine hoursare worked.