Machine hours and electricity costs for Wells Industries for 2011 were as follows: Machine Electricity Month Hours Costs January 2,000 $ 9,200 February 2,320 10,500 March 1,520 6,750 April 2,480...


Machine hours and electricity costs for Wells Industries for 2011 were as follows:















































































Machine



Electricity



Month



Hours



Costs



January



2,000



$  9,200



February



2,320



10,500



March



1,520



6,750



April



2,480



11,500



May



3,040



14,125



June



2,640



11,000



July



3,280



12,375



August



2,800



11,375



September



1,600



7,750



October



2,960



13,000



November



3,760



15,500



December



3,360



13,875





Required:






















A.



Using the

high-low method
, develop an estimate of
variable
electricity costs per machine hour.



______________________________



B.



Using the

high-low method
, develop an estimate of
fixed
electricity costs per month.



______________________________



C.



Using the high-low method, develop a
cost function (linear cost equation)
for use in


estimating monthly electricity costs.



______________________________



D.



Using the

cost equation

you developed in “C” above, estimate the
total electricity costs


for a month in which
3,000 machine hours
are worked.



______________________________