In the given project, the expected markup is 30%, four payments are expected to be paid to the contractor. The first three payments are expected to be as the following; first payment is 12,000 at the...


Please give me both answers as soon as possible. Thank you


In the given project, the expected markup is 30%, four payments are expected to be paid to the contractor. The first three payments are<br>expected to be as the following; first payment is 12,000 at the end of the first month; second payment is 16,000 at the end of second<br>month, and third payment is 22,000 at the end of fourth month. the value of the fourth payment assuming it will be paid at the end of<br>the fifth month, assuming 10% retentions, and that retentions will be paid back to the contractor at the end of the sixth month? Neglect<br>resources distribution in this project. Solve 9-14.<br>Find the project gross profit.<br>Duration<br>Activity<br>cost<br>20,000<br>,000<br>50,000<br>10,000<br>Activity<br>PredecessorRelationship<br>(months)<br>1.<br>1<br>A<br>FS<br>C<br>FS+1<br>FS<br>Answer:<br>Find the project price.<br>Answer:<br>

Extracted text: In the given project, the expected markup is 30%, four payments are expected to be paid to the contractor. The first three payments are expected to be as the following; first payment is 12,000 at the end of the first month; second payment is 16,000 at the end of second month, and third payment is 22,000 at the end of fourth month. the value of the fourth payment assuming it will be paid at the end of the fifth month, assuming 10% retentions, and that retentions will be paid back to the contractor at the end of the sixth month? Neglect resources distribution in this project. Solve 9-14. Find the project gross profit. Duration Activity cost 20,000 ,000 50,000 10,000 Activity PredecessorRelationship (months) 1. 1 A FS C FS+1 FS Answer: Find the project price. Answer:

Jun 11, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers