In mid-June, the GOLIATH program discovers that a Nunn-McCurdy cost
breach is expected to occur with respect to its Program Acquisition Unit Cost (PAUC). Over the next three months, the GOLIATH Program Manager will most likely be required to submit: (Select all that apply)A- Out-of-cycle Unit Cost ReportB- Quarterly Selected Acquisition ReportC- Out-of-cycle Consolidated Acquisition ReportD- Out-of-cycle Defense Acquisition Executive Summary