In earthwork construction of a highway section, using the data given in Table, if the free haul distance is 300 m. Calculated the total cost of borrow and overhaul. Where the overhaul cost is...

Please, I need to solve the question in less than an hour.In earthwork construction of a highway section, using the data given in Table, if the free haul distance is<br>300 m. Calculated the total cost of borrow and overhaul. Where the overhaul cost is $6.50/station.m' and<br>borrow is $10/m'.<br>Station<br>0+00<br>4+00<br>8+00<br>12400<br>16+00<br>20+00<br>Cumulative Volume.m<br>-200<br>+50<br>+300<br>+100<br>-100<br>

Extracted text: In earthwork construction of a highway section, using the data given in Table, if the free haul distance is 300 m. Calculated the total cost of borrow and overhaul. Where the overhaul cost is $6.50/station.m' and borrow is $10/m'. Station 0+00 4+00 8+00 12400 16+00 20+00 Cumulative Volume.m -200 +50 +300 +100 -100