In 2019, SM Residences entered into a 3-year agreement in to construct a condominium project for a contract price of P10,000,000. SM recognizes construction contract under the percentage of completion...


In 2019, SM Residences entered into a 3-year agreement in to construct a condominium project for a contract price of P10,000,000. SM recognizes construction contract under the percentage of completion method. For the year ended 2019, the following balances were found in SM’s books: Progress Billings P2,000,000; Accounts Receivable P1,000,000; Construction in Progress P3,500,000, Costs incurred to date P2,800,000. For 2020, the balances are Progress Billings P3,000,000; Accounts Receivable P1,200,000; Construction in Progress P6,500,000, Costs incurred to date 5,500,000. What is the percentage of completion in 2020?


Note: Please provide a good accounting form for the solution. Thank you!