If the mean time between failures for an instrument is 247 days and the mean time to repair is 3 days, calculate its availability. Data are collected by a manufacturer about a particular piece of...



If the mean time between failures for an instrument is 247 days and the mean time


to repair is 3 days, calculate its availability.



Data are collected by a manufacturer about a particular piece of machinery that is


used 24 hours/day, 7 days per week, recording both the intervals in days between


breakdowns and the time taken to repair each fault that causes a breakdown. The


following data are collected:


Times before breakdown ðin daysÞ: 13:3 4:3 12:7 17:8 14:2 20:1 15:6 8:9 8:1 11:5


Time to repair faults ðdaysÞ: 0:8 1:5 0:2 0:7 4:0 0:6 0:9 1:4 0:8 0:1


Calculate the mean time between failures, the mean time to repair, and the


availability of the machine.