If longest path is AEF (230 days), and the next path in length is ABF (200 days), what activity you will chose in order to start shortining project duration Normal Crash COST SLOPE Activity Normal...

Find the question,thanx.
If longest path is AEF (230 days), and<br>the next path in length is ABF (200<br>days), what activity you will chose in<br>order to start shortining project<br>duration<br>Normal Crash COST<br>SLOPE<br>Activity Normal Crash<br>duration Duration Cost<br>Cost<br>(days) (days<br>JA<br>120<br>100<br>12000 14000 100<br>20<br>15<br>1800 2800 200<br>40<br>30<br>16000 22000<br>30<br>20<br>1400 2000<br>50<br>40<br>3600 4800 120<br>60<br>45<br>13500 18000 300<br>Select one:<br>a. activity E<br>b. activity F<br>c. activity B<br>d. activity A<br>B.<br>

Extracted text: If longest path is AEF (230 days), and the next path in length is ABF (200 days), what activity you will chose in order to start shortining project duration Normal Crash COST SLOPE Activity Normal Crash duration Duration Cost Cost (days) (days JA 120 100 12000 14000 100 20 15 1800 2800 200 40 30 16000 22000 30 20 1400 2000 50 40 3600 4800 120 60 45 13500 18000 300 Select one: a. activity E b. activity F c. activity B d. activity A B.
what is the percent complete of the<br>following activity:<br>Total Quantity = 170 meter length<br>up to date Quantity = 100 meter length<br>%3D<br>.a<br>14%<br>b O<br>59%<br>70%<br>.C<br>17%<br>.d O<br>

Extracted text: what is the percent complete of the following activity: Total Quantity = 170 meter length up to date Quantity = 100 meter length %3D .a 14% b O 59% 70% .C 17% .d O