How difficult is it to add new activities to an existing project scheduling model? Answer this question by assuming that there are two other activities, labeled P and Q. Activity P moves selected...


How difficult is it to add new activities to an existing project scheduling model? Answer this question by assuming that there are two other activities, labeled P and Q. Activity P moves selected employees to temporary offices while installation occurs, and activity Q moves them back after installation is finished. Activity P has immediate predecessors D and E, immediate successor H, and duration three days. Activity Q has immediate predecessor L, immediate successor O, and duration three days. Find the new project completion time. Does the critical path change because of the new activity?



May 25, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here