Clients Rights and Obligations PREPARE A STEP BY STEP PROCEDURE TO ADVISE THE CLIENT OF THEIR SA CONTRACT TO BUILD. Using the Consumer Building Guide as a base, prepare a process to advise the client...

1 answer below »
Hi there, the Assessment task is to answer questions as in file attached. Thank you


Clients Rights and Obligations PREPARE A STEP BY STEP PROCEDURE TO ADVISE THE CLIENT OF THEIR SA CONTRACT TO BUILD. Using the Consumer Building Guide as a base, prepare a process to advise the client of the following: A) List what Licensing would be required by the builder and tradespeople to build their home. B) List what the builder actually does. C) Explain what Home Warranty Insurance is, who applies for it, when and what it covers. D) Provide a brief summary of the Development Application Process and what Regulatory Compliances need to be adhered to. E) Explain the role of the Accredited Certifier and the Principal Certifying Authority. F) Explain what the Statutory Warranties are and how they apply to the contract. G) Explain why and when a contract is necessary. H) Nominate what contract will be used and explain the client’s rights and obligations regarding: - - Prime Cost Items - Variations - Progress Claims & Payment of Claims - Dispute Resolution **Ensure you note where the information was obtained from and who the Author is for this question. How to Write a Procedure A Procedure is a step by step way of carrying out a task. Be specific – point form is acceptable but must be in the correct order If you use the point form system – always begin the section with a short preamble (only requires a sentence or two) outlining what the general procedure is then follow with the relevant steps. Include in the procedure - 1. WHO is responsible for each task 2. WHAT each task is 3. HOW each task is to be carried out 4. WHEN each task is to be implemented. You must include a copy of the relevant documents, when they are to be completed, by whom and when. Sometimes it is hard to know where to start. Set out your ideas in the following order: Rules 1. DO’S List - your rules first (policies) regarding each phase/section of the task 2. DO NOT List what must not be done PROCEDURE Step by Step tasks to carry out the role 1 - Who is responsible 2 - What needs to be done first 3 - What needs to be next 4 - Now list how it is to be done 5 - In what timeframe is each step to be carried out 6 - If it is applicable – nominate where the task should be carried out OR where information can be obtained 7 - If it is applicable – nominate how the process is to be recorded or documented SUPPORT DOCUMENTS 1.List the correct document that must accompany each document 2. Provide an example of each document 3.YOU MUST INCLUDE SAMPLE DOCUMENTS – OBLIGATIONS OF THE PARTIES 1.PRINCIPAL, CONTRACTOR, SUPERVISOR, SUBCONTRACTOR, WORKER etc 2.Where applicable insert what each officer’s obligations are CONTINGENCY List any ‘what to do if the wheels fall off’ REVIEW PROCESS 1.By Whom, When, Frequency 2.Report Process 3.Follow up Version 2 – Effective from January 2020 This guide has been developed by the QBCC in accordance with Schedule 1B of the Queensland Building and Construction Commission Act 1991 (‘the Act’) to assist home owners undertaking domestic building work with a contract price of $20,000 or more. It’s aimed at helping you avoid disputes and common pitfalls. COOLING-OFF PERIOD You may withdraw from the contract within 5 business days after the day you receive copies of both the signed contract (including any plans and specifications) and this guide. However, there are costs for home owners in withdrawing (generally $100 plus any out-of-pocket expenses reasonably incurred by the contractor up to the time of withdrawal). You must advise the contractor in writing that you are withdrawing under the cooling-off provisions in section 35 of Schedule 1B of the QBCC Act. QBCC LICENCE You should only deal with a QBCC-licensed contractor. If you engage an unlicensed contractor, your building work may not be covered under the Queensland Home Warranty Scheme. Before committing, check the contractor’s licence and history via the Online Licence Search on the QBCC website or by calling the QBCC. QLD HOME WARRANTY SCHEME Residential construction work valued at more than $3,300 is covered by the Queensland Home Warranty Scheme. The Scheme provides protection for home owners against non-completion, defective work and subsidence for up to 6 years from completion, provided a licensed contractor performs the work. The building contractor must collect the premium from the owner and pay it to the QBCC within 10 business days after the date the contract was entered into or before the contracted work is started (whichever is earlier). You should receive an email with a Notice of Cover and links to important information about the cover provided within 2 weeks of signing the contract. WARNING – COST PLUS AND CONSTRUCTION MANAGEMENT CONTRACTS QBCC strongly recommends home owners obtain formal legal advice before signing either of these types of contracts which increase your legal risk, reduce your Home Warranty Scheme protection and often result in disputes and cost overruns. COMMENCEMENT NOTICE For contracts priced at $20,000 or more, the contractor must give the owner a signed Commencement Notice within 10 business days of work commencing on site. The Notice must state the date work started on site and the Date for Practical Completion. CONTRACT PRICE For contracts priced at $20,000 or more, the contract price, if fixed, must be shown prominently on the first page of the contract schedule. If the contract price is not fixed, the method for calculating it, including any allowances, must be stated in the contract schedule. Allowances (items or services for which the price is not fixed when the contract is signed) should be kept to a minimum as the final cost often exceeds the estimate in the contract. The contract must also contain a warning about any provisions that may alter the contract price. DEPOSIT LIMITS The maximum deposit allowed (before work starts on site) is: • 10% where the total contract price is less than $20,000 • 5% where the price is $20,000 or more • 20% for a contract of any price where the value of the work to be performed off-site is more than 50% of the total contract price. PROGRESS PAYMENTS After the deposit is paid, owners and contractors are free to choose the number and timing of progress payments (if any) for their project, provided the amount claimed is directly related to work progress on site and proportionate to (or less than) the value of the work that relates to the claim. BUILDING APPROVALS AND INSPECTIONS Building inspections and approvals are the responsibility of a building certifier. Mandatory building inspections may be required at certain stages of construction. The contractor must give you copies of any certificates of inspection as soon as practicable after they receive them from the certifier. You can check the certifier’s licence via QBCC’s Online Licence Search. VARIATIONS Any change to the materials used or work to be performed under the contract is known as a ‘variation’. Variations are frequently the cause of cost overruns and building disputes. All variations must be agreed in writing by the home owner before the variation work commences and any price increase due to the variation can not be required to be paid until the variation work is started. DISPUTE PREVENTION To reduce the risk of a dispute, carefully check and be sure you understand the contract, including any plans and specifications, before signing. Discuss any questions with your contractor and seek independent legal advice if you still have concerns. Once construction starts, maintain regular communication and, where possible, site inspections with your contractor and pay promptly when required under the contract. CONSUMER BUILDING GUIDE Your contractor must give you this guide before you sign a contract priced at or over $20,000 http://www.qbcc.qld.gov.au Version 2 – Effective from January 2020 DISPUTE RESOLUTION If a dispute with your contractor occurs, firstly advise them in writing giving them a reasonable time to respond. If this doesn’t resolve the problem, explore QBCC’s free Early Dispute Resolution (EDR) service and your legal options. QBCC recommends you obtain independent legal advice before terminating the contract. Incorrect termination may have serious legal and financial consequences and reduce your protection under the Qld Home Warranty Scheme. EXTENSIONS OF TIME (EOTs) The contract must state the Date for Practical Completion for your project, or how the date is to be determined (e.g. 180 days from commencement). The Act sets out circumstances in which a contractor may seek to extend this date (e.g. if you approve a variation to the contract which involves extra work, or the work is interrupted by more rain than could reasonably have been anticipated). The contractor must give you a written EOT claim which you should carefully consider (not unreasonably reject) and respond to promptly in writing. If you approve the claim, the Date for Practical Completion will be extended by the period claimed. If you do not approve the claim, the extension is deemed ‘disputed’. LIQUIDATED DAMAGES (LDs) LDs are contractual payments to compensate a home owner for extra costs/losses they are likely to incur (e.g. extra rental costs) if the contractor fails to complete the work within the time allowed for in the contract (after allowing for legitimate extensions of time). Carefully consider what, if any, LD amount is appropriate for your project and ensure it is recorded in the contract. PRACTICAL COMPLETION AND HANDOVER You are not required to pay the final contract payment until all of the contracted work has been completed in accordance with the contract including any plans and specifications, all legal requirements, and either without any defects or omissions, or with only minor defects or minor omissions that will not unreasonably affect occupation. If you believe there are any minor defects or minor omissions, the contractor must give you a ‘defects document’ (listing agreed and non-agreed matters). This document
Answered Same DayJul 15, 2021

Answer To: Clients Rights and Obligations PREPARE A STEP BY STEP PROCEDURE TO ADVISE THE CLIENT OF THEIR SA...

Taruna answered on Jul 15 2021
156 Votes
3
Responses
A) The builders and trades-people require officially validated Queensland Building and Construction Commission license to build the homes. The licensing procedure is followed by the builder by filling out specific norm
s published by QBCC on its website. They are more like guidelines that one needs to fulfill in order to obtain license in building and construction. As the aspirer of home, one must check the license validity, renewed on annual bases so that it can be ensured that the builder is authorized by QBCC to enter into construction business. The issuing of license as well as permitting of work is solely subjected to QBCC; the builders have to adhere to the norms, as they are subjected to be changed at any time and make sure that they carry out validation process effectively.
B) Builders actually delay the process of validation deliberately as it takes time and energy both. Irrelevant notions are given and pretentions are made to violate the cooling-off provisions in section 35 of Schedule 1B of the QBCC Act as well. When someone permits construction over the approved land, the builders take advantage of the cooling off provision as most of the times, customers are not aware of this act fully, especially in the context of five days period given to withdraw the proposal. The builders take leverage of this cooling off period and extend the deadline of withdrawal or rather, they simply make the penalty over withdrawal as mandatory—which is not, if the withdrawing is taken on behalf of the customer in less than five days. Additionally, builders overlook the approval procedure to make sure that the land is safe and they are permitted to construct over it.
C) The home warranty scheme is designed for the customers who own residential construction work which is valued over $ 33, 00. It mainly covers the non-completed construction sites that are delayed up to six years. In other words, the owners of the given value construction work are covered under this scheme against any defect found at the construction site. Additionally, it is noteworthy here that home warranty scheme is dedicated to the work against the approved constructor only i.e. the work done by some non-approved builder does not come in its criteria. The builder must have a valid license and it should be well...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here