someTitle Contract Management1 975 Related Case Studies (from Related Workbook Exercises PMBOK Guide, Kerzner/Project Management (from Kerzner/Project Management 5th Edition, Reference Case Studies,...

1 answer below »
hi i have attached some attachments regarding the assessment can u please follow them.thank you


someTitle Contract Management1 975 Related Case Studies (from Related Workbook Exercises PMBOK Guide, Kerzner/Project Management (from Kerzner/Project Management 5th Edition, Reference Case Studies, 4th Edition) Workbook and PMP/CAPM Exam Section for the PMP Study Guide, 11th Edition) Certification Exam • The Scheduling Dilemma* • Multiple Choice Exam • Procurement • To Bid or Not to Bid* • Crossword Puzzle on Procurement Management • The Management Reserved* Management 19.0 INTRODUCTION In general, companies provide services or products based on the require- ments set forth in invitations for competitive bids issued by the client or the results of direct contract negotiations with the client. One of the most important factors in preparing a proposal and estimating the cost and profit of a project is the type of contract expected. The confidence by which a bid is prepared is usually dependent on how much of a risk the contractor will incur through the PMBOK® Guide, 5th Edition Chapter 12 Procurement Management *Case Study also appears at end of chapter. 1. The title of this chapter has been changed from Procurement Management in the Ninth Edition to Contract Management in this edition. Contract management includes procurement management. Procurement manage- ment is the buyer’s side of contract management, and sales/proposal management is the seller’s side of contract management. All those sellers (contractors) managing project contracts may not find it necessary to use the PMBOK® Guide, Chapter 12, because they may not be procuring anything. 19 c19.qxd 1/3/13 5:16 PM Page 975 Kerzner, Harold, and Harold R. Kerzner.
Project Management : A Systems Approach to Planning, Scheduling, and Controlling, John Wiley & Sons, Incorporated, 2013. ProQuest Ebook Central, http://ebookcentral.proquest.com/lib/apicollege/detail.action?docID=1113482. Created from apicollege on 2019-07-22 16:16:51. C op yr ig ht © 2 01 3. J oh n W ile y & S on s, In co rp or at ed . A ll rig ht s re se rv ed . contract. Certain types of contracts provide relief for the contractor since onerous risks2 exist. The cost must therefore consider how well the contract type covers certain high- and low-risk areas. Prospective clients are always concerned when, during a competitive bidding process, one bid is much lower than the others. The client may question the validity of the bid and whether the contract can be achieved for the low bid. In cases such as this, the client usu- ally imposes incentive and penalty clauses in the contract for self-protection. Because of the risk factor, competitors must negotiate not only for the target cost figures but also for the type of contract involved since risk protection is the predominant influential factor. The size and experience of the client’s own staff, urgency of completion, availability of qualified contractors, and other factors must be carefully evaluated. The advantages and disadvantages of all basic contractual arrangements must be recognized to select the optimum arrangement for a particular project. 19.1 PROCUREMENT Procurement can be defined as the acquisition of goods or services. Pro- curement (and contracting) is a process that involves two parties with different objectives who interact on a given market segment. Good pro- curement practices can increase corporate profitability by taking advantage of quantity discounts, minimizing cash flow problems, and seeking out quality suppliers. Because procurement contributes to profitability, procurement is often centralized, which results in standardized practices and lower paperwork costs. All procurement strategies are frameworks by which an organization attains its objectives. There are two basic procurement strategies: ● Corporate Procurement Strategy: The relationship of specific procurement actions to the corporate strategy. An example of this would be centralized procurement. ● Project Procurement Strategy: The relationship of specific procurement actions to the operating environment of the project. An example of this would be when the project manager is allowed to perform sole source procurement without necessar- ily involving the centralized procurement group, such as purchasing one ounce of a special chemical for an R&D project. Project procurement strategies can differ from corporate procurement strategies because of constraints, availability of critical resources, and specific customer requirements. Corporate strategies might promote purchasing small quantities from several qualified vendors, whereas project strategies may dictate sole source procurement. 976 CONTRACT MANAGEMENT PMBOK® Guide, 5th Edition Chapter 12 Introduction 12.1 Plan Procurement Management 2. Onerous risks are unfair risks that the contractor may have to bear. Quite often, the contract negotiations may not reach agreement on what is or is not an onerous risk. c19.qxd 1/3/13 5:16 PM Page 976 Kerzner, Harold, and Harold R. Kerzner.
Project Management : A Systems Approach to Planning, Scheduling, and Controlling, John Wiley & Sons, Incorporated, 2013. ProQuest Ebook Central, http://ebookcentral.proquest.com/lib/apicollege/detail.action?docID=1113482. Created from apicollege on 2019-07-22 16:16:51. C op yr ig ht © 2 01 3. J oh n W ile y & S on s, In co rp or at ed . A ll rig ht s re se rv ed . Procurement planning usually involves the selection of one of the following as the pri- mary objective: ● Procure all goods/services from a single source. ● Procure all goods/services from multiple sources. ● Procure only a small portion of the goods/services. ● Procure none of the goods/services. Another critical factor is the environment in which procurement must take place. There are two environments: macro and micro. The macro environment includes the general external variables that can influence how and when we do procurement. The PMBOK® Guide refers to this as “Enterprise Environmental Factors.” These include recessions, inflation, cost of borrowing money, whether a buyer or seller’s market exists, and unemployment. As an example, a for- eign corporation had undertaken a large project that involved the hiring of several con- tractors. Because of the country’s high unemployment rate, the decision was made to use only domestic suppliers/contractors and to give first preference to contractors in cities where unemployment was the greatest, even though there were other more qualified suppliers/contractors. The microenvironment is the internal procurement processes of the firm, especially the policies and procedures imposed by the firm, project, or client in the way that procure- ment will take place. This includes the procurement/contracting system, which contains four processes according to the PMBOK® Guide, Fourth Edition: ● Plan Procurements ● Conduct Procurements ● Administer Procurements ● Close Procurements It is important to understand that, in certain environments such as major projects for the Department of Defense (DoD), the contracting process is used as the vehicle for tran- sitioning the project from one life-cycle phase to the next. For example, a contract can be awarded for the design, development, and testing of an advanced jet aircraft engine. The contract is completed when the aircraft engine testing is completed. If the decision is made at the phase gate review to proceed to aircraft engine production, the contracting process will be reinitiated for the new effort. Thus, the above four PMBOK® Guide processes would be repeated for each life-cycle phase. As the project progresses from one phase to the next, and additional project knowledge is acquired through each com- pleted phase, the level of uncertainty (and risk) is reduced. The reduction in project risk allows the use of lower-risk contracts throughout the project life cycle. During higher-risk project phases such as conceptual, development, and testing, cost-type contracts are tradi- tionally used. During the lower-risk project phases such as production and sustainment, fixed-priced contracts are typically used. It is also important to note that the above four PMBOK® Guide processes focus only on the buyer’s side of contract management. Procurement 977 PMBOK® Guide, 5th Edition 2.1.5 Enterprise Environmental Factors c19.qxd 1/3/13 5:16 PM Page 977 Kerzner, Harold, and Harold R. Kerzner.
Project Management : A Systems Approach to Planning, Scheduling, and Controlling, John Wiley & Sons, Incorporated, 2013. ProQuest Ebook Central, http://ebookcentral.proquest.com/lib/apicollege/detail.action?docID=1113482. Created from apicollege on 2019-07-22 16:16:51. C op yr ig ht © 2 01 3. J oh n W ile y & S on s, In co rp or at ed . A ll rig ht s re se rv ed . Contract management is defined as “art and science of managing a contractual agree- ment throughout the contracting process.”3 Since contracts involve at least two parties— the buyer and the seller (contractor), contract management processes are performed by both the buyer and seller. The seller’s contract management processes, which correspond to the buyer’s processes, consist of the following activities4: ● Presales Activity: The process of identifying prospective and current cus- tomers, determining customer’s needs and plans, and evaluating the competitive environment. ● Bid/No Bid Decision-Making: The process of evaluating the buyer’s solicitation, assessing the competitive environment and risks against the opportunities of a potential business deal, and then deciding whether to proceed. ● Bid/Proposal Preparation: The process of developing offers in response to a buyer’s solicitation or based on perceived buyer needs, for the purpose of per- suading the buyer to enter into a contract. ● Contract Negotiation and Formation: The process of reaching a common understanding of the nature of the project and negotiating the contract terms and conditions for the purpose of developing a set of shared expectations and understandings. ● Contract Administration: The process of ensuring that each party’s performance meets contractual requirements. ● Contract Closeout: The process of verifying that all administrative matters are concluded on a contract that is otherwise physically complete. This involves com- pleting and settling the contract, including resolving any open items. As can be seen from the previous discussion, the last two phases of the seller’s contract management processes are identical to the buyer’s contract management processes. This is because the buyer and seller are both performing the same contract management activities and working off of the same contract document. 19.2 PLAN PROCUREMENTS The first step in the procurement process is the planning for purchases and acquisitions, specifically the development of a procurement plan that states what to procure, when, and how. This process includes the following: ● Defining the need for the project ● Development of the procurement statement of work, specifications, and work breakdown structure 978 CONTRACT MANAGEMENT PMBOK® Guide, 5th Edition 12.1 Plan Procurements 3. Gregory A. Garrett and Rene G. Rendon, Contract Management: Organizational Assessment Tools (Ashburn, VA: National Contract Management Association, 2005), p. 270. 4. See note 3. c19.qxd 1/3/13 5:16 PM Page 978 Kerzner, Harold, and Harold
Answered Same DayApr 23, 2021SBM1202

Answer To: someTitle Contract Management1 975 Related Case Studies (from Related Workbook Exercises PMBOK...

Abhishek answered on Apr 29 2021
159 Votes
Final Report on
Comparison of Rialto and Eureka tower construction process
Student
Subject
TABLE OF CONTENTS
1    Summary    4
2    PROJECTS    4
2.1    Architectural Features    5
2.2    Structural features    5
Construction    5
2.3    Impacts On Business    6
ACKNOWLEDGEMENT    11
REFERENCES    12
1. Summary
The purpose of this report is “Comparison of Rialto and Eureka Towers construction process”. It aims at understanding the differences between the construction process between, not only two buildings, but also between two centuries when one being pri
mitive than the other. Emphasizing on the procurement management techniques for supply chain management with suitable solutions for every problem statement.
Both of the buildings are categorized under high rise buildings. They foster solutions for problems like
Population density
With better medical facilities and medicines, the general mortality rate has been reduced to considerable amount. This causes more population in a specific place thus causing need for shelter. Also, as there is always movement of population from rural areas to city place causes burden for the city.
Land shortfall
There has been land scarcity both nationally and internationally as the population is growing at an alarming pace globally, This shortfall of land has led to increase in their prices thus less affordable.
These problems call for measures to provide shelter to the growing population by the sustainable economical utilization of land.
Historically, high rise buildings have been efficient and aesthetic developments representing symbol of power and power status of any person, place, society or culture.
1. PROJECTS
Here we examine the two iconic towers of Melbourne belonging to the high rise or skyscraper family namely the Eureka and the Rialto towers.
Rialto Tower
It is a skyscraper situated in Melbourne and was the tallest building housing offices i.e was an office building when it opened its doors in 1986. The structure consists of two adjoining towers, with a 43-story wing linked to the 63-story main tower. The salient feature of this building was the observation deck that featured in Melbourne for the first time ever. It was originally built in 1889 by Grollo group.
In 1979 redevelopment proposal was placed before MELBOURNE City Council and construction began in 1982 and was completed 4 years later after a few objections. It was approved as a redevelopment project that used traditional construction processes as not much literature is available for reference about the project.
Eureka Towers
Another skyscraper built by Grocon (Grollo group and partners) which had the honour of being the tallest building of the world when it was opened in 2006 but later succumbed the position to Burj Khalifa. It still holds the record of highest residential building of the world.
As per Designbuild-network site, “The tower is named after the Eureka Stockade rebellion during the 1854 Victoria gold rush (the building crown is gold coloured with a red stripe representing the gold and the bloodshed). The horizontal lines on the building represent the markings on a ruler and the blue façade with white lines is supposed to represent the blue and white flag of the stockade. Also, the markings on a surveyor’s measuring staff are depicted by the white horizontal stripes.”
Various new techniques were employed in the construction of the building. These included foundation, continuous auger piles and high walls.
1. Architectural Features
The height of the Eureka Tower building is 297.3 m or 975 ft with observation deck known as Eureka Skydeck located on the 88th floor. It has 556 apartments serviced by 13 elevators travelling at speed reaching upto 9m/s. The building is relatively slender with a critical structural challenge of resisting the wind loading and control building oscillations in cost effective manner. This is achieved by building water tank on the roof for damping.
In comparison to Eureka tower, the height of Rialto tower is short by 46.3 m so it stands at 251 m but was the first in Melbourne to have skyscraper public observation deck on the 56th floor. It is predominantly an office building with 55 floors on the taller tower and 43 floors on the shorter North tower.
1. Structural features
Construction
Due to the proximity to Yarra River, the water table is in close vicinity of the Eureka tower. In fact, it is jut 2m below the tower site as the site area was a reclaimed swampland. This resulted in formation of 2 layers of Basalt above the base layer of Silurian siltstone bedrock necessary for foundation and normally occurred at a depth of 35 m below the surface.
To counteract the menace of swampland resulting in Basalt layer formation, the construction of the building foundation was carried out using special methods involving prepressurised concrete and through employment of slipform method using reinforced concrete. The method involved anchoring, 3 m into the siltstone, 243 continuous augered piles with 750 mm diameter and 28 bored piles of 1500 mm diameter, where conditions dictated.
As for the Rialto tower, there were not enough challenges of this sort as it was a redevelopment process and foundations were already laid. Even, if they were not, the construction technology would not have been at the level, in that era, where these methods would have been thought for....
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here