Here is a question and answer. I need the answer for e)PROBLEM 5 (8 points)DayACPVEV65$550$735$678a) Calculate the cost variance (CV). (2 points)-550 The Cost Variance of the project is $128b)...


Here is a question and answer. I need the answer for e)PROBLEM 5 (8 points)DayACPVEV65$550$735$678a) Calculate the cost variance (CV). (2 points)-550 The Cost Variance of the project is $128b) Calculate the cost performance index (CPI). (2 points)The CPI of the project is EV/AC = 678/550 = 1.23c) Calculate the schedule variance (SV). (2 points)The schedule variance of the project is EV-PV -735 = -$57d) Calculate the schedule performance index (SPI). (2 points)The SPI of the project is 678/735 = 0.92e) Given these data, what should a project manager do with respect to this project?



May 15, 2022
SOLUTION.PDF

Get Answer To This Question

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here
April
January
February
March
April
May
June
July
August
September
October
November
December
2025
2025
2026
2027
SunMonTueWedThuFriSat
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
2
3
00:00
00:30
01:00
01:30
02:00
02:30
03:00
03:30
04:00
04:30
05:00
05:30
06:00
06:30
07:00
07:30
08:00
08:30
09:00
09:30
10:00
10:30
11:00
11:30
12:00
12:30
13:00
13:30
14:00
14:30
15:00
15:30
16:00
16:30
17:00
17:30
18:00
18:30
19:00
19:30
20:00
20:30
21:00
21:30
22:00
22:30
23:00
23:30