1 | P a g e Production and Distribution Network for QuickClean Background QuickClean, a rapidly growing company based in Melbourne, Australia, manufactures throwaway paper towel and mop cloth and...

1 answer below »
Here are the case study and the tips for the assignment
and remember need to use excel and excel solver to answer all case questions. thanks


1 | P a g e     Production and Distribution Network for QuickClean  Background  QuickClean,  a  rapidly  growing  company  based  in  Melbourne,  Australia,  manufactures  throwaway paper  towel  and mop  cloth  and  supplies  its products  to  supermarkets  in  the  whole Australia. Tony Richardson, director of supply chain at QuickClean, believes that the  company is facing a critical supply chain problem as the current production and distribution  network  is  inefficient. This  is mainly due  to  the significant  increase  in  transportation costs  over  the past  few years which  can  continue  in  the  coming years. The  current  centralized  supply network design has resulted in long journey distance in distribution hence very high  distribution cost. A quick decision on building one or more new plants in other cities could  save the company significant amounts in transportation expense in the future.  QuickClean was founded in the late 1990s and produced throwaway paper towel and mop  cloth that could make household chores a lot simpler. Current and ultimate demand for the  two products in the eight states of Australia is shown in Table 1. The company currently has  a factory in Melbourne only that produces both products for all the states in Australia. The  paper towel production line has a capacity of 12 million units per year, an annualized fixed  cost  (e.g., maintenance,  insurance, and other overheads) of $2 million, and a variable  cost  (e.g.,  production, materials,  etc.)  of  $0.5  per  unit.  The mop  cloth  production  line  has  a  capacity of 10 million units per year, an annualized fixed cost of $1.5 million, and a variable  cost of $0.8 per unit. The  current  transportation  costs per unit  (same  for paper  towel and  mop cloth) are shown in Table 2.    Table 1 – Current (C) and ultimate (U) annual demand for QuickClean from all states in Australia    State  Paper Towel  Demand  Mop Cloth  Demand    State  Paper Towel  Demand  Mop Cloth  Demand  New South  Wales (NSW)  3,093,000 (C)  3,827,000 (U)  2,577,000 (C)  3,125,000 (U)  South  Australia (SA)  663,000 (C)  821,000 (U)  553,000 (C)  670,000 (U)  Queensland  (QLD)  1,876,000 (C)  2,322,000 (U)  1,564,000 (C)  1,896,000 (U)  Victoria (VIC)  2,500,000 (C)  3,093,000 (U)  2083,000 (C)  2526,000 (U)  Northern  Territories (NT)  96,000 (C)  119,000 (U)  80,000 (C)  97,000 (U)  Tasmania  (TAS)  202,000 (C)  249,000 (U)  168,000 (C)  204,000 (U)  Western  Australia (WA)  1,016,000 (C)  1,257,000 (U)  847,000 (C)  1,027,000 (U)  Australian  Capital  Territory  (ACT)  154,000 (C)  192,000 (U)  128,000 (C)  155,000 (U)    Tony has identified Sydney, Brisbane; Adelaide; and Perth as potential sites for new plants  (see  Figure  1).  Each  new  plant  could  have  a  paper  towel  production  line,  a mop  cloth  production  line,  or  both.  Construction  cost  for  a  new  plant  is  $8 million with  a  single  2 | P a g e     production  line  and  $10 million with  both  production  lines  regardless  of  location. Using  newer production technology, a new paper towel  line has a capacity of 8 million units per  year, an annual fixed cost of $1.5 million, and a variable production cost of $0.4 per unit. A  new mop cloth  line has a capacity of 6 million units per year, an annual  fixed cost of $1.2  million, and a variable production  cost of $0.7 per unit.  It  is  expected  that ultimately  the  demand at the eight states would be as shown in Table 1. Tony is planning for the long‐term  production and distribution network of the company. His primary objective is to minimize  the  total  construction,  fixed, variable,  and  transportation  costs. Nonetheless, his boss  also  wants him to take into account strategic considerations. That is, if two options are similar in  cost but one is strategically favourable, he may recommend it for the board’s consideration.  So,  Tony  has  to  decide  whether  to  build  any  new  plant(s),  where  to  build  and  which  production  line(s)  to put  into  the  new plant(s),  given  the  current  transportation  costs  (in  Table 2) which can be double in the long run.  Table 2 – Current transportation costs for QuickClean from plants (existing and new) to all states    NSW  QLD  NT  WA  SA  VIC  TAS  ACT  Melbourne  $0.11  $0.28  $0.35  $0.37  $0.18  $0.04  $0.06  $0.07  Sydney  $0.04  $0.25  $0.37  $0.43  $0.22  $0.11  $0.14  $0.04  Brisbane  $0.11  $0.19  $0.34  $0.46  $0.25  $0.20  $0.25  $0.15  Adelaide  $0.17  $0.24  $0.27  $0.27  $0.09  $0.09  $0.15  $0.14  Perth  $0.49  $0.44  $0.32  $0.11  $0.29  $0.41  $0.44  $0.46    For the purpose of his analysis, Tony uses a period of ten years (Year 1 to Year 10) as a basis  for comparison. To make things simple, he assumes that the current year is Year 0 and the  next year is Year 1. From Year 1 to Year 10, the ultimate demands from each of the states will  the used. Transportation costs may or may not change. But if they do, he again assumes that  the change would take effect in Year 1 and the new costs could maintain throughout the 10‐ year period. He also assumes that any new plant(s), if built, are available in Year 1 and the  construction cost  is  incurred  immediately. Therefore,  the 10‐year  total cost should  include  construction cost (if any), annualized fixed cost, variable production cost and transportation  cost from Year 1 to Year 10. This will be used for comparison between options.    Case Questions  Assume you were Tony and you need to answer the following questions from your boss:  1. Assuming the present is Year 0, what is the current (or Year 0) total annual cost of serving  the entire nation from Melbourne only given the current transportation cost?  2. (a) Given the current transportation cost, what is the 10‐year (Year 1 to Year 10) total cost  of  serving  all  the  states  from Melbourne  only?  (b) What  if  the  transportation  costs were  double their current value?  3 | P a g e     3. At current transportation costs, would you recommend adding any plant(s)? If so, where  should the plant(s) be built and what line(s) should be included? (Note: You can assume that  the Melbourne plant will be maintained at  its  current  capacity but  could be  run  at  lower  utilization or even just one production line.)  4. Would your decision  in Question 3 be different  if transportation costs were double their  current value?  5.  If  Tony  could  design  a  new  network  from  scratch  (assume  that  he  did  not  have  the  Melbourne plant but could build  it,  if needed, at  the same costs and capacity  for  the new  plant  specified  in  the  case),  what  production  network  would  you  recommend  if  transportation costs remain at their current value?  6. Would your decision  in Question 5 be different  if transportation costs were double their  current value?  7. If Tony were required to set up only one production line at each plant, and assuming he  could design a new network from scratch as he did in Question 5, what production network  would you recommend if transportation costs remain at their current value?  8. Would your decision  in Question 7 be different  if transportation costs were double their  current value?  9.  Based  on  the  outcomes  of  the  above  analyses  and  taking  into  account  the  need  for  strategic  consideration,  what  long‐term  production  and  distribution  network  will  you  recommend to the boss and why?                     Figure 1 – Demand regions and plant sites for QuickClean  Page 1 of 5 Tips for OMGT1053 Assignment 2 Production and Distribution Network Design for QuickClean Dear Students, Here are some tips to help you complete the quantitative assignment of the course. The assignment is about network optimization and will require the use of Solver to find the optimal solutions. For this assignment, you will need to first develop a generic model on a spreadsheet and validate it. Then, with proper modifications in terms of model input, e.g., demand figures, unit transportation costs, and constraints in Solver, e.g., condition that reflects the requirement of a particular option, the model can be used as a tool to help find the optimal production and distribution network design for QuickClean - the case company. You can set up the model using the SunOil example as a reference. Despite the fact that there is only one product in the SunOil example but two in the QuickClean case, both problems are identical in nature and are categorized as Capacitated Facility Location Problems. It means that their mathematical formulations are very similar, although some minor modification is needed in the case of QuickClean as production and transportation costs are separated. Basically, the objective function is a cost functional comprising fixed and variable operating costs. In the QuickClean case, fixed costs are the annualized costs for the production lines. Variable costs are production and material costs which vary with the volume of production. There are also transportation costs which are also variable as they vary with the amount of products distributed to customers. If new plants are built (for some of the options), there will be construction costs as well but they can be added to the total cost later. This will make the problem formulation a lot simpler. The constraints in the QuickClean case include demand constraint (i.e., all demand must be met), capacity constraint (i.e., available capacity cannot be exceeded), non-negativity constraint (i.e., values of all variables cannot be negative) and binary constraint (i.e., production lines can either be open or close only). There is no need for integer constraint (number of plants must be in whole number) because it is unlikely that there will be more than one plant at one potential site or city. The best way to go is to first create a model representing the current or the as-is situation, i.e., Year 0. This will be needed to answer Case Question 1. To work out the total operating cost for Year 0, you do not need Solver at all because everything is fixed and there is no alternative course of action, hence no need for optimization. However, it will still be good to use Solver to find the solution because this will allow you to (i) cross-check if your cost figure is correct and (ii) have a generic model that can be copied and modified for option or scenario testing. As the layout of all the other models will be the same as that of the generic model, and the Solver setups will be quite similar, you can simply copy the generic model and rename it to become another model for a particular option or scenario. There are four options to investigate in the QuickClean case. Total cost in a 10-year period (Year 1 to Year 10) is used as a basis for comparison. For each option, there are two scenarios: (1) unit transportation costs remain unchanged as they are; and (2) unit transportation costs are double in value. The four options are as follows: (1) Producing and distributing from Melbourne only to all demand regions (or states) (Q2a and Q2b); (2) Producing and distributing from Melbourne and other cities, such as Brisbane, Sydney, Adelaide, and Perth (Q3 and Q4); (3) Producing and distributing from any cities (i.e., Melbourne is no longer a must) (Q5 and Q6); and (4) Producing and distributing at any cities with only one production line at each plant (Q7 and Q8). Upon analysing the outcome of the four options (each with two scenarios), you will need to make a recommendation on which option to take considering cost and strategic value (Q9). For each option, you will need two models to find the optimal network configurations under the two scenarios. As mentioned above, this can be done easily by copying the validated generic model to a new spreadsheet and rename it. Next, alter the input parameters of the model and revise the constraints in the Solver dialogue box where appropriate to reflect the condition of the option. Then, run Solver to get the optimal solution for that scenario. Basically, the workbook should comprise 10 worksheets. Nine (9) of them Page 2 of 5 should be models (for Q1, Q2(a), Q2(b), Q3, Q4, Q5, Q6, Q7 and Q8), each representing a scenario under an option. The last worksheet (for Q9) is not a model but a summary of the model outputs and the final recommendation upon comparison and analysis of the findings. NOTE: DO NOT use only one single spreadsheet or a summary report in the Excel workbook for everything and expect the assessor to create the models for the different options or scenarios from scratch to check your answers. Marks will be deducted if the required nine models (each in one sheet) and one summary sheet are not provided. Unlike the SunOil example in which only operating cost is considered, we have to take into account construction cost of the new plants in the QuickClean case in deciding on the optimal long-run production and distribution network configuration. For simplicity reason, you can use the same formulation of the SunOil example (with minor modification) for the QucikClean case. In other words, it means that the model for the QuickClean case also does not have construction cost in the objective function. As such, you cannot make recommendation simply based on the Solver solutions. Instead, they can help you work out the total annual costs for production and distribution for the different options. You can use them to work out the 10-year total operating costs. Then, if new plants are built under an option, construction cost can be added to the 10-year operating costs. These 10-year total costs (fixed, variable, transportation, and construction), together with their corresponding configurations, can then be compared to determine which option would be most desirable from both a cost and a strategic perspective. Here are some suggestions for you to set up the model: 1. There are many ways to build the model. You are encouraged to use your own design keeping in mind that the model logic needs to be easy to follow and understand while the model layout is simple and clear. Proper colour scheme and legend should be used where appropriate to make
Answered Same DaySep 25, 2021OMGT1053

Answer To: 1 | P a g e Production and Distribution Network for QuickClean Background QuickClean, a rapidly...

Guneet answered on Sep 29 2021
148 Votes
PRODUCTION AND DISTRIBUTION NETWORK OPTIMIZATION
NETWORK OPTIMIZATION
Student Name:
Name of the Project: Production and Distribution Network Optimization
Professor:
September 29, 2019
Solution to Case Study to all the questions:
1)
    
    STATES
    CURRENT DEMAND PAPER TOWEL
    CURRENT DEMAND MOP CLOTH
    TOTAL DEMAND
    RATES OF TRANSPORTATION PER UNIT
    TOTAL COST OF TRANSPORTATION ($)
    1
    New south Wales
    3093000
    2577000
    5670000
    $ 0.11
    623700
    2
    Queensland
    1876000
    1564000
    3440000
    $ 0.28
    963200
    3
    Northern Territories
    96000
    80000
    176000
    $ 0.35
    61600
    4
    Western Australia
    1016000
    847000
    1863000
    $ 0.37
    689310
    5
    South Australia
    663000
    553000
    1216000
    $ 0.18
    218880
    6
    Victoria
    2500000
    2083000
    4583000
    $ 0.04
    183320
    7
    Tasmania
    202000
    168000
    370000
    $ 0.06
    22200
    8
    Australian Capital Territory
    154000
    128000
    282000
    $ 0.07
    19740
    
    TOTAL
    9600000
    8000000
    17600000
    
    $ 2781950
The total cost of transportation is $2781950 for distribution from Melbourne.
2a)
    REFF FOR ANS 2a)
    STATES
    CURRENT DEMAND PAPER TOWEL
    CURRENT DEMAND MOP CLOTH
    TOTAL DEMAND
    RATES OF TRANSPORTATION PER UNIT
    CURRENT COST OF TRANSPORTATION
    10 Year COST OF TRANSPORTATION
    1
    New south Wales
    3093000
    2577000
    5670000
    0.11
    623700
    6237000
    2
    Queensland
    1876000
    1564000
    3440000
    0.28
    963200
    9632000
    3
    Northern Territories
    96000
    80000
    176000
    0.35
    61600
    616000
    4
    Western Australia
    1016000
    847000
    1863000
    0.37
    689310
    6893100
    5
    South Australia
    663000
    553000
    1216000
    0.18
    218880
    2188800
    6
    Victoria
    2500000
    2083000
    4583000
    0.04
    183320
    1833200
    7
    Tasmania
    202000
    168000
    370000
    0.06
    22200
    222000
    8
    Australian Capital Territory
    154000
    128000
    282000
    0.07
    19740
    197400
    
    TOTAL
    9600000
    8000000
    17600000
    
    2781950
    27819500
The above table shows 10 yr transportation cost at current rate of transportation. It comes to $27819500.
2b)
    REFF FOR ANS 2b)
    STATES
    CURRENT DEMAND PAPER TOWEL
    CURRENT DEMAND MOP CLOTH
    TOTAL DEMAND
    DOUBLED RATE OF TRANSPORTATION PER UNIT
    10 Year COST OF TRANSPORTATION
    1
    New south Wales
    3093000
    2577000
    5670000
    0.22
    12474000
    2
    Queensland
    1876000
    1564000
    3440000
    0.56
    19264000
    3
    Northern Territories
    96000
    80000
    176000
    0.7
    1232000
    4
    Western Australia
    1016000
    847000
    1863000
    0.74
    13786200
    5
    South Australia
    663000
    553000
    1216000
    0.36
    4377600
    6
    Victoria
    2500000
    2083000
    4583000
    0.08
    3666400
    7
    Tasmania
    202000
    168000
    370000
    0.12
    444000
    8
    Australian Capital Territory
    154000
    128000
    282000
    0.14
    394800
    
    TOTAL
    9600000
    8000000
    17600000
    
    55639000
The above table displays total 10Yr cost of transportation if transportation rate per unit is doubled.
It comes to $55639000, which is very high for the tenure. Quickclean should focus on minimizing the cost.
3) At current transportation cost it is not recommended to add any plant. To justify this see the calculations below.
First calculation has been done for determining transportation cost from all the 5 locations available.
    TRANSPORTATION COST CURRENT DEMAND
    LOCATIONS
    Amount ($)
    MELBOURNE
    2781950
    SYDNEY
    2787740
    BRISBANE
    3549520
    ADELAIDE
    2956920
    PERTH
    7077340
As we see from above that Sydney and Melbourne have similar total transportation cost on current demand, we will calculate a combination of plants running in Melbourne and Sydney both. We can’t close Melbourne plant as the new plant capacity will not fulfill the total current demand of Quickclean.
Assumptions:
We have taken transportation cost cheaper from a particular place is considered.
Melbourne towel plant is running at half capacity.
We cannot close any product line in Melbourne as the supplies...
SOLUTION.PDF

Answer To This Question Is Available To Download

Related Questions & Answers

More Questions »

Submit New Assignment

Copy and Paste Your Assignment Here