Answer To: Task 2 – Risk Management Strategy Review Instructions to Learners: • This summative assessment can...
Hartirath answered on Sep 25 2021
Project Management (
2
)
Student Name:
Unit Name:
University Name:
Date:
Contents
First project: Website hosting and redevelopment, and maintenance services for destination: Australia. 3
Overview 3
Second project: Re-development of intranet 11
Overview 11
Project scope management 11
Third project: Database for community engagement- SAAS CRM 18
Overview: 18
Project scope management 19
Risk Management Plan 25
Introduction 26
Analysis and Evaluation 26
Task 2 27
References 1
First project: Website hosting and redevelopment, and maintenance services for destination: Australia.
Overview
The purpose of the risk management plan is to record key information about the technical upgrade of the archive site Australia to ensure that the project will be effectively managed from the beginning to the implementation (Aryanto et al., 2014). In order to ensure that the main stakeholders understand and agree with the scope and methods of the project, recommend and approve the recommendations in this document. Some key information included in this risk management plan includes:
· Project Objectives
· Project scope management
· Project risk management
· Project schedule management
· Project change management
· Project communication management
· Project cost management
· Project procurement management
· Project personnel management
· Project stakeholder management
· Project governance
The objective of this risk management plan is to ensure a smooth transition from proprietary content management content (CMS) to commonly used CMS sites. The business value will be the data users contribute to the website (Aryanto et al., 2014). The expected result of the project is that website will be use as a data collection portal in Australia, and users can contribute information about photography collections to the website. The needs for the success criteria are that website requires to having modern interface, a friendly design suitable for each ages, English proficiency moreover computer literacy. Websites need to interact succesfully with available application programming interfaces (APIs) (Boesso & Kumar, 2016). Nevertheless, there is other option, which will be available until December 31, 2019.
Project scope management
The scope of project will be defined in WBS statement as the table below
Figure 1: The WBS roadmap of the project.
To measure the scope of the project, we will use 3 steps.
· Step 1: Collect requirements
The primary step is to examine the expectations and needs of the project stakeholders to achieve the project goals. The primary step is to find out the requirements as well as prospect of key project stakeholders to achieve the project goals (Chi et al., 2020). Therefore, the website wants to have ability to effectively conrol large amounts of information, the system should be completely operational in two weeks after proposed contract takes effect, and website can also be modernized in future.
· Step 2: Define the scope for the project
Step second is to develop a project scope report (esk, 2013). The project scope reports provide a detailed explanation of the whole thing included in project, as shown below.
· Description of product range.
· Criteria of Product acceptance.
· Project deliverables.
· Item excluded.
· Project constraints.
· Project vision.
After reaching agreement with major stakeholders, the PSS will become the basis for project decision-making.
· Step 3: Create the work breakdown structure
The last step is to make a WBS for project.
· The PM should be answerable for approving and managing the scope of the plan, or then sending it to each stakeholder to make clear the final decision.
Project risk management
· Risks will be reported in forms used to report risks, and will be monitored and evaluated through forms and communication channels (Jakhar, 2016). Each form that needs to be submitted and answered through communication channels can improve the efficiency of interaction and problem solving.
· In any case, the risk must first be reported to the team leader. If the team leader cannot resolve or has no decision-making authority, the risk is transferred to the project manager for resolution.
Project schedule management
There is a team role list and task schedule, and the main role of project team or individuals will assume these roles. The following list will be considered project roles.
· Project Manager
· System engineer.
· Software engineer.
· Test Engineer.
· Technical application support.
Deliverable List
Recipients
Delivery Date
Delivery Method
Comments
Design Database
Software Engineer team
Monday of the first week
Online transfer + USB backup
Design Complete
System Engineer team
Friday of the second week
Online transfer + USB backup
Development Complete
Testing Engineer team
Friday of the second week
Online transfer + USB backup
Website Complete
Customer
Monday of the fourth week
Online transfer + USB backup
Figure 2: The deliverable list table.
Figure 3: The schedule table.
Project change management
· A change within the scope of project management is anything that will change or affect the project, task, process, structure, and job function (Jeong et al., 2011). Therefore, only the project manager can decide whether an item can be changed.
· Change requests need to be submitted, monitored and evaluated through communication channels.
Figure 4: The change requests process.
Project communication management
Type of Communication
Communication Schedule
Typical Communication Mechanism
Who Initiates
Recipient
Status Report
Every 3 days
Team meeting
PM
Project team and external stakeholders
Effort Tracking and Schedule Report
every day
Email
Team leader
PM
Project Review
every day
Face to face
PM
Project team
Risk Mitigation Status
As mitigation action are finished
Email
answerable team member
PM
Need Changes
As changes are accepted
Email or change control tool
Both external and internal stakeholder
Affected project applicants
Figure 5: The communication time table.
Project cost management
· The PM will be answerable for allocating the total budget to every project group, and the leader of each team will be answerable for controlling, monitoring and reporting the budget (Luna-Nevarez & Hyman, 2012).
· The budget report requires to monitoring in the communication channel.
· The program budget and expenditure are shown in the table below.
Project procurement management
· The team leader of each team in the project will post purchase orders to make the project.
· The technical application support team will collect purchase requests, be responsible for the relationship with suppliers, and handle contracts, purchases and other activities (Pennay, 2013).
· The project manager must clarify, evaluate, and accept before the technical application supports team actions.
Project staffing management
Each team will have 2 members and 1 leader; apart from the technical support team, there will be only 2 members (Bourgeon, 2007).
· Software engineer team requirements:
· Have 1 week to complete the work
· Have comprehensive skills in building a website platform.
· Become a professional software engineer when working with the team.
· Develop requirements for the engineer team:
· Has 1 week to complete the work
· Have comprehensive skills in building a website platform.
· Become a professional software engineer when working with the team.
· Test engineer team requirements:
· Has 1 week to complete the work
· Has a comprehensive website platform performance test capability.
· Become a professional software engineer when working with the team.
· Technical support team requirements:
· Need to support all other teams in the project team during the project.
· Will report directly to the PM.
Project stakeholder management
List of project stakeholders:
· Project manager.
· The organization is the owner of the website.
· Suppliers of related materials or other resources.
Employee:
· The technical support team will be responsible for collecting and reporting stakeholder information for the project leader (Ponnappa, 2014).
· The strategies for managing stakeholders are as follows
Name of key stakeholders
Strategy to manage
Interests
The organization, who is the owner of the website.
Keep informed
Supporter
Suppliers of related materials or other resources.
Manage closely
Supporter
Employees.
Monitor
Supporter
Figure 7: The strategy to manage stakeholders of the project.
Project governance
· The project manager will be the person with the highest responsibility in the plan.
· The website owner will have the right to examine the behavior of project manager to ensure that the behavior of the PM is suitable for the scope of the project (Dalcher, 2009).
· The PM and team leader will meet every three days to talk about the task progress of each team and the problems faced by each team, and will communicate and review decisions through the communication channels.
· The project manager and website owner will meet on Fridays every week to discuss the progress of the project.
Second project: Re-development of intranet
Overview
The function of the risk management plan is to record key information about the clean energy regulator Intranet redevelopment to SharePoint 2013 to ensure that the project will be effectively managed from the beginning to the implementation. In order to ensure that the main stakeholders understand and agree with the scope and methods of the project (Lewis, 2013), recommend and approve the recommendations in this document. Some key information included in this risk management plan includes:
· Project Objectives
· Project risk management
· Project schedule management
· Project change management
· Project personnel managemen
· Project governance
The goal of the risk management strategy is to ensure that the development of clean energy regulator intranet is transferred to SharePoint 2013. The business value of this project is that internal employees can use the sharing point 2013 as safe location to organize, store, access and share information on some device (Lewis, 2013).
Project scope management
The scope of project will be defined in WBS statement as the table below
Figure 1: The project WBS roadmap
To measure the scope of project, we will use 3 steps.
Step 1: Collect needs:
The initial step is to verify the expectations and needs of main project stakeholders to achieve the project goals (Lewis, 2013). Therefore, the project needs to ensure that internal personnel can use SharePoint 2013 as a safe location to store, manage, access, and share data from some device.
Step 2: Explain the scope of the project:
Step second is to develop a PSS. The PSS describes in detail all the content included in the project, as shown below.
· Description of product range.
· Project deliverables.
· Item excluded.
· Project constraints.
· Project vision.
After reaching agreement with major stakeholders, the project scope statement will become the basis for project decision-making.
Project risk management
· Risks will be reported in forms used to report risks, and will be monitored and evaluated through forms and communication channels. Each form that needs to be submitted and answered through communication channels can improve the efficiency of interaction and problem solving (Gladden, 2012).
· In any case, the risk must first be reported to the team leader. If the team leader cannot resolve and has no decision-making authority, the risk is transferred to the project manager for resolution.
Project schedule management
There is a team role list and task schedule, and the main project group roles as well as individuals will assume these roles. The following list will be considered project roles.
· Project Manager
· System engineer.
· Software engineer
· Test Engineer
· Technical application support.
Deliverable List
Recipients
Delivery Date
Delivery Method
Comments
Access to computer systems within the organization.
Software Engineer team
In the beginning of the first week
Online transfer + USB backup
Checking and complete installation Share Point 2013 program.
System Engineer team
At the end of the first week
Online transfer + USB backup
Complete system
Testing Engineer team
In the beginning of the first week
Online transfer + USB backup
Complete
The organization
At the end of the second week (Gladden, 2012)
Online transfer + USB backup
Figure 2: The deliverable list table.
Figure 3: The schedule table.
Project change management
· A change within the scope of project management is anything that will change or affect the project, task, process, structure, and job function. Therefore, only the project manager can decide whether an item can be changed (Jakhar, 2016).
· Change requests need to be submitted, monitored and evaluated through communication channels.
· Both external and internal members of the project can issue change requests to make changes when essential, however they need to go throughout the following process.
Figure 4: The change requests process
Project communication management
Type of Communication
Communication Schedule
Typical Communication Mechanism
Who Initiates
Recipient
Status Report
Every 3 days
Team meeting
Project manager
Project team or external...