Hawkins Corporation began construction of a motel on March 31, 2021. The project was completed on April 30, 2022. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period:$5,100,000, 6% note$14,540,000, 10% bondsConstruction expenditures incurred were as follows:
The company’s fiscal year-end is December 31.Required:Calculate the amount of interest capitalized for 2021 and 2022.(Round weighted average interest rate to 2 decimal places and final answers to the nearest whole dollar.)